20 connections, ~400m cable28 work items6 sectionsToronto, Canada
About This Project
Estimate for installing a 500-metre electrical supply network. Includes cable trench excavation, conduit installation, medium-voltage cable laying, transformer pad preparation, junction boxes, street lighting connections, grounding systems, and surface reinstatement. Based on Canadian electrical utility standards.
Scope of Works
Design & Permits (3)Transformer Station (4)Trench & Cable Installation (7)Distribution (4)Earthing & Street Lighting (5)Testing & Commissioning (5)
Get a Personalized Estimate for Your Project
Enter your area, city, and specific requirements to get a detailed cost estimate with local pricing, project timeline, and cost breakdown.
Data Source:DDC Pricing DB — English·55,719 items·CWICR
City Adjustment
🏛 Toronto, Canada
Your city matches the base — coefficients ×1.00
PPP Coefficients
Labor Factor
×
click to adjust
Material Factor
×
click to adjust
Equipment Factor
×
click to adjust
Prices from a professional construction database (55,719 items), adjusted to your city using construction-specific Purchasing Power Parity (PPP). Coefficients can be manually adjusted.
Detection Confidence
50%
Cost Breakdown
iHow the total cost is distributed: labor, materials, equipment, overhead, and profit margins
C$747,169.14Direct Cost
Labor (55%)C$61,493.97
Materials (15%)C$16,552.71
Equipment (9%)C$9,630.70
Overhead (101%)C$112,075.39
Profit (77%)C$85,924.46
Cost / m²
Labor
C$153.73
Materials
C$41.38
Equipment
C$24.08
Overhead
C$280.19
Profit
C$214.81
Grand Total
C$277.28
Materials / Labor
0.27
Direct Cost %
673.7%
21 work items across 6 categories, 66 resources
Cost Flow
6iVisual flow of the total budget through work categories, showing proportional cost distribution
Complete BOQ: 28 work items for Electrical Supply Network
4 work item(s) not found in pricing DB for language 'en'.
Categories
6iCost distribution by work category — earthwork, structure, facade, MEP, finishes, etc.
Category
Cost
Cost / m²
Share
Distribution
C$14,302.25
C$35.76
12.9%
Design & Permits
C$715.49
C$1.79
0.6%
Transformer Station
C$53,638.32
C$134.10
48.4%
Testing & Commissioning
C$6,335.21
C$15.84
5.7%
Earthing & Street Lighting
C$13,979.11
C$34.95
12.6%
Trench & Cable Installation
C$856,198.63
C$2,140.50
772.0%
Top Items
Description
Total
Block substation with a voltage of 35 kV according to t…
C$49,624.98
Cable protection with metal gutters on the stairwell wi…
C$15,883.49
Installation of sand cushions 30 cm thick
C$6,512.79
Control cabinet for microprocessor-based centralization…
C$5,656.43
Subscriber or group connection with installation of box…
C$4,833.38
What-If Scenarios
iExplore how changes in material, labor, or equipment costs affect the total project budget
Optimistic (-10%)
C$99,820.74
↓ C$11,091.19 savings
Labor -10% · Materials -10% · Equipment -10%
Base Estimate
C$110,911.93
Deterministic
Labor ×1.00 · Materials ×1.00 · Equipment ×1.00
Pessimistic (+15%)
C$127,548.72
↑ C$16,636.79 increase
Labor +15% · Materials +15% · Equipment +15%
Custom Scenario: Adjust cost components
Labor0%
Materials0%
Equipment0%
Custom Scenario Total Cost
C$110,911.93
Clicking Apply will update PPP coefficients and recalculate all line items
Project Schedule
≈2 monthsiProject timeline with critical path method (CPM), Gantt chart, and resource allocation
2
months
69
days
6
phases
2
Critical Path
12
Peak workers
2,497
Labor Hours
Site PreparationEarthworksStructural FrameworkFlooringMEP FinishTesting and CommissioningCumulative Cost
Labor Hours by Phase
MEP Finish
1,495 hours
Earthworks
646 hours
Structural Framework
256 hours
Testing and Commissi
72 hours
Site Preparation
50 hours
Flooring
28 hours
Monthly Cash Flow
3 monthsiMonthly cost distribution and cumulative S-curve showing how project spending builds over time
59%
M1
96%
M2
100%
M3
Month
days
Monthly Cost
%
Cumulative
%
M1
1–30
C$65,410.91
59.0%
C$65,410.91
59%
M2
31–60
C$40,629.51
36.6%
C$106,040.43
96%
M3
61–69
C$4,871.50
4.4%
C$110,911.93
100%
Daily Cash Flow
10 weeks
2%
D1
13%
D7
25%
D13
39%
D19
51%
D25
61%
D31
70%
D37
80%
D43
88%
D49
93%
D55
96%
D61
99%
D67
100%
D69
Week
days
Weekly Cost
%
Cumulative
%
W1
D1–D7
C$14,048.27
12.7%
C$14,048.27
13%
W2
D8–D14
C$16,561.49
14.9%
C$30,609.76
28%
W3
D15–D21
C$16,980.36
15.3%
C$47,590.13
43%
W4
D22–D28
C$14,306.29
12.9%
C$61,896.42
56%
W5
D29–D35
C$12,300.73
11.1%
C$74,197.15
67%
W6
D36–D42
C$12,300.73
11.1%
C$86,497.88
78%
W7
D43–D49
C$11,397.73
10.3%
C$97,895.61
88%
W8
D50–D56
C$5,979.70
5.4%
C$103,875.31
94%
W9
D57–D63
C$3,788.95
3.4%
C$107,664.26
97%
W10
D64–D69
C$3,247.67
2.9%
C$110,911.93
100%
Line Items
21 itemsiDetailed work items grouped by category with quantities, unit prices, and resource breakdown
▼Design & Permits3 itemsC$715.49
#
Code
Description
Qty
Unit
Unit Price
Total
1
KAVO_KATO_PUDXME_KASAm
Preparation of tachogenerators for testing, commissioning and start-up, connection to the electrical network, weight: up
1.0
1 set(Design & Permits)
pcs
C$39.24
C$49.64
C$39.24 +15% C$5.89+10% C$4.51
Labor Materials Equipment
Type
Resource
Qty
Unit
Unit Price
Cost
Worker Category 1
1.09
hrs
C$29.69
C$32.36
Paper twine, diameter RI.SA mm
0.01
kg
C$8.35
C$0.08
Rubberized cotton insulating tape for electrical installation and repair work, black, width 20 mm, thickness KA.TOSA mm
0.42
m
C$0.27
C$0.11
Welding electrodes for welding low-alloy and carbon steels UONI 13/45, E42A, diameter 4-5 mm
0.08
kg
C$6.58
C$0.53
Flexible jumpers, type PGS-50
0.10
10 pcs
C$57.52
C$5.75
Welding machines for manual arc welding, welding current up to 350 A
0.27
Machine hours
C$1.53
C$0.41
2
KALI_KASA_KATOLI_KAME
Installation of utility service starter blocks
1.0
1 set(Design & Permits)
pcs
C$17.90
C$22.65
C$17.90 +15% C$2.69+10% C$2.06
Labor Materials Equipment
Type
Resource
Qty
Unit
Unit Price
Cost
2nd grade worker
0.37
hrs
C$17.38
C$6.44
Grade 3 worker
0.08
hrs
C$18.98
C$1.56
Mobile cranes, lifting capacity 16 t
0.09
Machine hours
C$66.77
C$5.87
Personnel: 1 person-hour/machine-hour
0.09
Machine hours
C$15.24
C$1.34
Flatbed trucks, load capacity up to 5 tons
0.07
Machine hours
C$25.93
C$1.87
Personnel: 1 person-hour/machine-hour
0.07
Machine hours
C$11.34
C$0.82
3
RIKA_KAME_KADXRI_KARIm
Relay semi-automatic locking control panel for sections with devices: route control
1.0
1 set(Design & Permits)
pcs
C$508.46
C$643.20
C$508.46 +15% C$76.27+10% C$58.47
Labor Materials Equipment
Type
Resource
Qty
Unit
Unit Price
Cost
Worker Category 1
17.60
hrs
C$28.89
C$508.38
MA-22 oil paint, lithopone white
0.01
kg
C$3.82
C$0.04
Technical acetone, grade I
0.01
kg
C$4.02
C$0.04
▼Transformer Station1 itemsC$49,624.98
#
Code
Description
Qty
Unit
Unit Price
Total
4
KAVO_KAME_KARISA_KASAm
Block substation with a voltage of 35 kV according to the diagram: one working, sectioned by a switch, busbar system, tr
1.0
1 set(Transformer Station)
pcs
C$39,229.23
C$49,624.98
C$39,229.23 +15% C$5,884.39+10% C$4,511.36
Labor Materials Equipment
Type
Resource
Qty
Unit
Unit Price
Cost
Worker Category 1
1,193.00
hrs
C$25.79
C$30,772.70
B-70 aviation gasoline
0.01
t
C$5,637.29
C$56.38
Technical petroleum jelly
4.90
kg
C$11.96
C$58.62
Welding electrodes for welding low-alloy and carbon steels UONI 13/45, E42A, diameter 4-5 mm
18.30
kg
C$5.89
C$107.80
Bolts with nuts and washers for construction
2.95
kg
C$8.26
C$24.35
Coarse calico, width 1640 mm, surface density 125 g/m2
1.98
10 m
C$24.85
C$49.19
Hot-rolled steel strip, steel grades St3sp, St3ps, dimensions 50x5 mm
0.02
t
C$2,402.63
C$48.06
Unedged coniferous boards, natural moisture content, length RI-NE.SA m, width 100-250, thickness 30-50 mm, grade III
0.03
m3
C$734.54
C$22.03
MA-0115 oil paint, mummy, iron minium
36.50
kg
C$4.94
C$180.38
A671 marking tags
0.36
100 pcs
C$25.61
C$9.22
Mobile cranes, lifting capacity 16 t
74.70
Machine hours
C$63.51
C$4,743.94
Personnel: 1 person-hour/machine-hour
74.70
Machine hours
C$18.38
C$1,373.10
Hydraulic lifts, lifting height 10 m
1.92
Machine hours
C$5.30
C$10.19
Personnel: 1 person-hour/machine-hour
1.92
Machine hours
C$13.68
C$26.26
Filling and pressure testing units, flow rate up to 300 m3/h
8.12
Machine hours
C$131.59
C$1,068.54
Personnel: 1 person-hour/machine-hour
8.12
Machine hours
C$15.73
C$127.73
Flatbed trucks, load capacity up to 5 tons
12.80
Machine hours
C$24.66
C$315.71
Personnel: 1 person-hour/machine-hour
12.80
Machine hours
C$13.68
C$175.11
Welding machines for manual arc welding, welding current up to 350 A
43.70
Machine hours
C$1.37
C$59.92
▼Trench & Cable Installation4 itemsC$29,836.02
#
Code
Description
Qty
Unit
Unit Price
Total
5
KALI_KAME_KASAPU_MEPU
Installation of sand cushions 30 cm thick
400.0
400 m(Trench & Cable Installation)
m
C$12.87
C$6,512.79
C$5,148.44 +15% C$772.27+10% C$592.07
Labor Materials Equipment
Type
Resource
Qty
Unit
Unit Price
Cost
Worker Category 1
178.40
hrs
C$20.34
C$3,628.44
Universal front-end pneumatic wheeled single-bucket loaders, nominal capacity of main bucket RI.NE m3, load capacity 5 t
2.88
Machine hours
C$68.67
C$197.76
Personnel: 1 person-hour/machine-hour
2.88
Machine hours
C$16.18
C$46.61
Pneumatic rammers powered by mobile compressor units
3.20
Machine hours
C$0.13
C$0.40
Mobile screw compressors with electric motor, pressure up to 1 MPa (10 atm), capacity up to 5 m3/min
3.20
Machine hours
C$7.05
C$22.56
Installation of sand cushions 30 cm thick
400.00
m
C$3.13
C$1,252.67
6
KAVO_KARI_TODXPU_KAPUm
Cable line, number of cables in line up to 4, cable core cross-section up to 16 mm2
200.0
200 m(Trench & Cable Installation)
m
C$14.70
C$3,719.87
C$2,940.61 +15% C$441.09+10% C$338.17
Labor Materials Equipment
Type
Resource
Qty
Unit
Unit Price
Cost
Worker Category 1
106.24
hrs
C$26.03
C$2,765.17
Welding electrodes for welding low-alloy and carbon steels UONI 13/45, E42A, diameter 4-5 mm
0.38
kg
C$6.08
C$2.31
Bolts with nuts and washers for construction
0.30
kg
C$8.53
C$2.56
Wire cotter pins
0.20
kg
C$6.18
C$1.23
MA-0115 oil paint, mummy, iron minium
0.80
kg
C$5.10
C$4.08
Cable anchors
0.16
100 pcs
C$344.46
C$55.11
Mobile cranes, lifting capacity 16 t
0.84
Machine hours
C$65.57
C$55.08
Personnel: 1 person-hour/machine-hour
0.84
Machine hours
C$18.98
C$15.94
Flatbed trucks, load capacity up to 5 tons
0.84
Machine hours
C$25.47
C$21.39
Personnel: 1 person-hour/machine-hour
0.84
Machine hours
C$14.13
C$11.87
Welding machines for manual arc welding, welding current up to 350 A
4.14
Machine hours
C$1.42
C$5.86
7
KAVO_KARI_TODXPU_KAPUm
Cable line, number of cables in line up to 4, cable core cross-section up to 16 mm2
200.0
200 m(Trench & Cable Installation)
m
C$14.70
C$3,719.87
C$2,940.61 +15% C$441.09+10% C$338.17
Labor Materials Equipment
Type
Resource
Qty
Unit
Unit Price
Cost
Worker Category 1
106.24
hrs
C$26.03
C$2,765.17
Welding electrodes for welding low-alloy and carbon steels UONI 13/45, E42A, diameter 4-5 mm
0.38
kg
C$6.08
C$2.31
Bolts with nuts and washers for construction
0.30
kg
C$8.53
C$2.56
Wire cotter pins
0.20
kg
C$6.18
C$1.23
MA-0115 oil paint, mummy, iron minium
0.80
kg
C$5.10
C$4.08
Cable anchors
0.16
100 pcs
C$344.46
C$55.11
Mobile cranes, lifting capacity 16 t
0.84
Machine hours
C$65.57
C$55.08
Personnel: 1 person-hour/machine-hour
0.84
Machine hours
C$18.98
C$15.94
Flatbed trucks, load capacity up to 5 tons
0.84
Machine hours
C$25.47
C$21.39
Personnel: 1 person-hour/machine-hour
0.84
Machine hours
C$14.13
C$11.87
Welding machines for manual arc welding, welding current up to 350 A
4.14
Machine hours
C$1.42
C$5.86
8
MEKA_KANE_KATOPU_MENEm
Cable protection with metal gutters on the stairwell with passage through the landing along the wall: wooden or brick
400.0
400 m(Trench & Cable Installation)
m
C$31.39
C$15,883.49
C$12,556.12 +15% C$1,883.42+10% C$1,443.95
Labor Materials Equipment
Type
Resource
Qty
Unit
Unit Price
Cost
Average workload TO.KA
164.00
hrs
C$24.34
C$3,991.59
Plastic dowels with screws, diameter 12 mm, length 70 mm, screw diameter 8 mm, screw length 70 mm
40.00
100 pcs
C$52.44
C$2,097.64
MA-0115 oil paint, mummy, iron minium
16.00
kg
C$5.25
C$84.04
Natural drying oil
8.00
kg
C$7.03
C$56.24
Metal gutter, dimensions 48x1000 mm
400.00
pcs
C$6.12
C$2,446.71
Overlay staples
12.00
100 pcs
C$206.51
C$2,478.16
Installation machines for laying and installing cables based on a vehicle
20.00
Machine hours
C$53.37
C$1,067.40
Personnel: 1 person-hour/machine-hour
20.00
Machine hours
C$16.72
C$334.34
▼Distribution4 itemsC$14,302.25
#
Code
Description
Qty
Unit
Unit Price
Total
9
KAVO_KATO_SALIRI_KADXm
Cabinet-type control unit or distribution point (cabinet), installed: in a niche, height and width up to 1300x850 mm
5.0
5 pcs(Distribution)
pcs
C$217.30
C$1,374.41
C$1,086.49 +15% C$162.97+10% C$124.95
Labor Materials Equipment
Type
Resource
Qty
Unit
Unit Price
Cost
Worker Category 1
10.30
hrs
C$26.90
C$277.03
Welding electrodes for welding low-alloy and carbon steels UONI 13/45, E42A, diameter 4-5 mm
1.00
kg
C$5.96
C$5.97
Bolts with nuts and washers for construction
0.85
kg
C$8.36
C$7.11
Custom-made steel structures from rolled steel
0.10
t
C$6,755.30
C$675.53
MA-0115 oil paint, mummy, iron minium
0.25
kg
C$5.00
C$1.25
Mobile cranes, lifting capacity 16 t
0.95
Machine hours
C$64.30
C$61.09
Personnel: 1 person-hour/machine-hour
0.95
Machine hours
C$18.61
C$17.68
Flatbed trucks, load capacity up to 5 tons
0.95
Machine hours
C$24.97
C$23.72
Personnel: 1 person-hour/machine-hour
0.95
Machine hours
C$13.85
C$13.16
Welding machines for manual arc welding, welding current up to 350 A
2.85
Machine hours
C$1.39
C$3.96
10
MEKA_KANE_KATOPU_MEDXm
Subscriber or group connection with installation of boxes or AZU from a pole or rack to the wall
20.0
20 pcs(Distribution)
pcs
C$191.04
C$4,833.38
C$3,820.85 +15% C$573.13+10% C$439.40
Labor Materials Equipment
Type
Resource
Qty
Unit
Unit Price
Cost
Worker Category 1
40.00
hrs
C$21.93
C$877.22
Mounting material kits for subscriber protection devices
0.20
100 pcs
C$752.29
C$150.46
UK-2 junction boxes
2.00
10 pcs
C$4.43
C$8.85
PS-1-1 flat clamps (SA.SA-VO.NE mm)
0.40
100 pcs
C$223.92
C$89.57
PTZ 2x1.2 transmission cable
0.20
1000 m
C$248.66
C$49.73
TF-12 linear pin insulators
6.00
100 pcs
C$353.49
C$2,120.93
Installation machines for laying and installing cables based on a vehicle
7.60
Machine hours
C$52.51
C$399.08
Personnel: 1 person-hour/machine-hour
7.60
Machine hours
C$16.45
C$125.01
11
KAVO_KARI_TODXPU_KAPUm
Cable line, number of cables in line up to 4, cable core cross-section up to 16 mm2
200.0
200 m(Distribution)
m
C$14.70
C$3,719.87
C$2,940.61 +15% C$441.09+10% C$338.17
Labor Materials Equipment
Type
Resource
Qty
Unit
Unit Price
Cost
Worker Category 1
106.24
hrs
C$26.03
C$2,765.17
Welding electrodes for welding low-alloy and carbon steels UONI 13/45, E42A, diameter 4-5 mm
0.38
kg
C$6.08
C$2.31
Bolts with nuts and washers for construction
0.30
kg
C$8.53
C$2.56
Wire cotter pins
0.20
kg
C$6.18
C$1.23
MA-0115 oil paint, mummy, iron minium
0.80
kg
C$5.10
C$4.08
Cable anchors
0.16
100 pcs
C$344.46
C$55.11
Mobile cranes, lifting capacity 16 t
0.84
Machine hours
C$65.57
C$55.08
Personnel: 1 person-hour/machine-hour
0.84
Machine hours
C$18.98
C$15.94
Flatbed trucks, load capacity up to 5 tons
0.84
Machine hours
C$25.47
C$21.39
Personnel: 1 person-hour/machine-hour
0.84
Machine hours
C$14.13
C$11.87
Welding machines for manual arc welding, welding current up to 350 A
4.14
Machine hours
C$1.42
C$5.86
12
MENE_KAVO_KAKAME_KATO
Installation of metal cabinets for sanitary systems: on a wall or in a niche weighing more than 20 to 30 kg
20.0
20 pcs(Distribution)
pcs
C$172.91
C$4,374.59
C$3,458.17 +15% C$518.73+10% C$397.69
Labor Materials Equipment
Type
Resource
Qty
Unit
Unit Price
Cost
Worker Category 1
46.68
hrs
C$22.41
C$1,046.00
Electricity
1.80
kWh
C$92.55
C$165.27
Plastic dowels, diameter 14 mm, length 70 mm
0.80
100 pcs
C$2,781.82
C$2,226.83
Mobile cranes, lifting capacity 16 t
0.16
Machine hours
C$66.36
C$10.62
Personnel: 1 person-hour/machine-hour
0.16
Machine hours
C$19.11
C$3.06
Flatbed trucks, load capacity up to 5 tons
0.16
Machine hours
C$25.77
C$4.12
Personnel: 1 person-hour/machine-hour
0.16
Machine hours
C$14.22
C$2.27
▼Earthing & Street Lighting5 itemsC$13,979.11
#
Code
Description
Qty
Unit
Unit Price
Total
13
KAVO_KARI_TOPUNE_KAPUm
Grounding of individual contact network structures in a tunnel
5.0
5 pcs(Earthing & Street Lighting)
pcs
C$170.17
C$1,076.35
C$850.87 +15% C$127.63+10% C$97.85
Labor Materials Equipment
Type
Resource
Qty
Unit
Unit Price
Cost
Worker Category 1
22.80
hrs
C$27.68
C$631.12
Bolts with nuts and washers for construction
25.00
kg
C$8.60
C$215.11
Grounding adjustment nuts
0.10
100 pcs
C$46.48
C$4.64
14
KAME_KARI_KATODX_KAME
Reinforcement of the brow of earthwork slopes with turf tape
400.0
400 m(Earthing & Street Lighting)
m
C$6.29
C$3,181.95
C$2,515.37 +15% C$377.31+10% C$289.27
Labor Materials Equipment
Type
Resource
Qty
Unit
Unit Price
Cost
Worker Category 1
65.20
hrs
C$21.49
C$1,401.47
Firewood cut into 2 groups (pine, alder), length up to 1 m
1.00
m3
C$128.67
C$128.67
Standard rolled turf
110.00
m2
C$8.95
C$984.46
Non-tipping wheelbarrows, capacity ME.PU m3
2.32
Machine hours
C$0.33
C$0.77
15
KAVO_KARI_TOVOTO_KARIm
Installation of a street light kit with autonomous power supply (250 W solar panel): without anti-vandal fencing
Monte Carlo · 10KiMonte Carlo simulation (10,000 iterations) showing completion probability at different confidence levels
76days
P50
50% probability the project finishes within this timeframe. Median scenario based on Monte Carlo simulation.
86days
P80
80% probability — recommended planning basis. Accounts for common delays and uncertainties.
96days
P95
95% probability — conservative estimate. Covers nearly all risk scenarios including severe delays.
+17days
Buffer
Recommended time buffer to add to the deterministic schedule. Covers typical construction uncertainties.
Base Cost (P50)
C$110,911.93
Budget (P80)
C$124,549.28
Maximum (P95)
C$137,618.40
Contingency
+12.3%
Recommended cost reserve based on schedule risk analysis — C$13,637.35 Recommended Budget: C$124,549.28
Deterministic 69 days
P50 76 days
P80 86 days
P95 96 days
P50 P80 P95
Based on Monte Carlo simulation with 10,000 iterations using PERT distribution for each phase duration.
Peak: 12
2,497 man-hours
2 crit. phases
Cost Risk Analysis
Monte Carlo · 10,000 iterations
Monte Carlo simulation of construction cost uncertainty
Cost Percentiles
C$1,130,323.63
P10
C$1,162,135.22
P25
C$1,207,493.72
P50
C$1,269,096.80
P80
C$1,299,244.12
P90
Cumulative Probability (S-Curve)
+5.1%
Recommended Contingency (P80 − P50)
Reserve to cover likely cost overruns with 80% confidence — C$61,603.08
Top Risk Drivers
Category
Work Item
Risk Share
Trench & Cable Installation
Insulation of steel pipelines with polymer tapes w
99.6%
Transformer Station
Block substation with a voltage of 35 kV according
0.4%
Design & Permits
Preparation of tachogenerators for testing, commis
0.0%
Design & Permits
Installation of utility service starter blocks
0.0%
Design & Permits
Relay semi-automatic locking control panel for sec
0.0%
Transformer Station
Mobile 6 kV mine substation with transformer capac
0.0%
Trench & Cable Installation
Installation of sand cushions 30 cm thick
0.0%
Trench & Cable Installation
Cable line, number of cables in line up to 4, cabl
0.0%
Sensitivity Analysis
±10%iImpact of ±10% change in each cost component on the total project cost
This tornado chart shows how a ±10% change in each cost category affects the total estimate. The wider the bar, the greater the cost impact — helping identify which cost drivers carry the most risk and where tighter cost control may be needed.
Decrease ← → IncreaseImpact
Overhead101% of total
±C$11,207.54±10.1%
Profit77% of total
±C$8,592.45±7.7%
Labor55% of total
±C$6,149.40±5.5%
Materials15% of total
±C$1,655.27±1.5%
Equipment9% of total
±C$963.07±0.9%
Cost Summary
iFinal cost breakdown with direct costs, overhead, profit, and grand total
Labor
C$61,493.97
55%
Materials
C$16,552.71
15%
Equipment
C$9,630.70
9%
Direct Cost
C$747,169.14
Overhead
C$112,075.39
101%
Profit
C$85,924.46
77%
Grand Total
C$110,911.93
100%
EUR equivalent
€69.190,22
USD equivalent
$79,741.73
GBP equivalent
£60,370.55
Estimate Classification
AACE 18R-97
AACE International Recommended Practice 18R-97
2
ClassClass 2
Typical PurposeCost Control
Expected Accuracy Range:-15% / +20%
Project Definition Level:30–75%
Cost Benchmark
Office · North America
Comparison of estimated cost/m² against market reference ranges
Low 1,800
▲ Typical 2,500
High 3,800
▼ Your Estimate 1,505 EUR/m²
Below typical range · 0.60x ratio to typical
Methodology & Assumptions
iCalculation methodology, data sources, and key assumptions underlying this estimate
Data Source
DDC Pricing DB — English
Confidence Level
50%
Overhead Rate
15%
Profit Rate
10%
Items Matched
21
Assumptions
Costs adjusted by location-specific labor, material, and equipment factors
Exchange rates are offline reference rates and may differ from market rates
All amounts exclude VAT / sales tax
This estimate is for preliminary budgeting only — not a binding quotation
Included in Estimate
All labor, materials, and equipment per defined scope
Overhead and profit margins as specified
Location-adjusted pricing factors applied
Excluded from Estimate
VAT / sales tax
Permits, licenses, and legal fees
Temporary works and site facilities
Design and engineering fees
Prices current as of 2026-03-16 · No cost escalation or inflation adjustment applied
The cost depends on your location, materials chosen, and project scope. Use our calculator with your specific city to get an instant estimate based on 28 verified work items from our database of 55,719 construction prices.
What work items are included in this estimate?
This BOQ includes 28 work items covering Design & Permits, Transformer Station, Trench & Cable Installation, Distribution, Earthing & Street Lighting, Testing & Commissioning. Each item is matched to unit rates from our verified pricing database spanning 9 languages and 36 locations worldwide.
How long does Electrical Supply Network take?
Duration depends on project size and complexity. A typical 20 connections, ~400m cable project takes approximately 4 weeks. Our calculator generates a detailed Gantt chart with phase-by-phase scheduling.
How accurate is this estimate?
Our estimates use verified construction pricing data with location-specific adjustments (PPP factors). The Monte Carlo simulation provides P10-P90 confidence intervals. For formal budgeting, we recommend a Class 3 AACE estimate with local contractor quotes.
What does a electrical supply network include?
Estimate for installing a 500-metre electrical supply network. Includes cable trench excavation, conduit installation, medium-voltage cable laying, transformer pad preparation, junction boxes, street lighting connections, grounding systems, and surface reinstatement. Based on Canadian electrical utility standards.