Commercial · C07

Medical Clinic / Dental Practice Fit-Out Cost Estimate — 150 m²

150 m² 34 work items 7 sections Toronto, Canada

About This Project

Detailed fit-out estimate for a 100 m² medical clinic or dental practice. Includes clinical room partitions with lead lining where required, medical gas installations, specialized ventilation, clinical lighting, vinyl flooring, reception area, sterilization room, accessible washrooms, and IT/telecom infrastructure for medical systems.

Scope of Works

Demolition & Preparation (2)Partitions & Doors (4)Finishes (6)MEP — Electrical (6)MEP — HVAC (3)MEP — Plumbing (6)Reception & Furniture (7)

Get a Personalized Estimate for Your Project

Enter your area, city, and specific requirements to get a detailed cost estimate with local pricing, project timeline, and cost breakdown.

Calculate Cost for My Project →
Full Professional Estimate
0 items changed

Overview

iKey project metrics at a glance — total cost per m², labor and material shares, and estimated duration
Source: Text Query
C$670.26
Cost / m²
54.2%
Labor
21.0%
Materials
193 days
Est. Duration

Work Items

30 items iAdjust quantities or remove items, then recalculate. Click item name to jump to details.
Replacement: two-compartment sinks5pcsC$1,989.48
Swivel chair10pcsC$2,108.00
Chair: lightweight dental3pcsC$873.87

Project Context

iInput parameters, location adjustment factors, and detection confidence for this estimate
Source
Hospital
150 m² · 30 items
SourceText Query
Work Items30 items · 7 Categories
CurrencyC$ CAD
LanguageEnglish
Date05 Apr 2026
Medical Clinic / Dental Practice Fit-Out 150 m² Toronto Canada
Cost / m²
C$670.26
150 m²
Est. Duration
6 months
193 days
Overhead
15%
C$14,162.60
Direct Costs
94%
C$94,417.36
Location
Toronto, Canada
Americas
×1.07
Estimate Overview
C$100,539.52
C$670.26 / m² · 6 months (193 days)
Labor 54% Materials 21% Equipment 4% Overhead 14% Profit 11%
Contingency (P80)
+8%
C$8,445.32
Budget (P80)
C$108,984.84
recommended
Resources
83
49 mat · 13 lab · 21 equ
Overhead + Profit
14% + 11%
C$25,020.59
Pricing Methodology
Data Source: DDC Pricing DB — English · 55,719 items · CWICR
City Adjustment
🏛 Toronto, Canada
Your city matches the base — coefficients ×1.00
PPP Coefficients
Labor Factor
×
click to adjust
Material Factor
×
click to adjust
Equipment Factor
×
click to adjust
Prices from a professional construction database (55,719 items), adjusted to your city using construction-specific Purchasing Power Parity (PPP). Coefficients can be manually adjusted.
Detection Confidence
50%

Cost Breakdown

iHow the total cost is distributed: labor, materials, equipment, overhead, and profit margins
C$94,417.36Direct Cost
Labor (54%)C$54,531.26
Materials (21%)C$21,120.71
Equipment (4%)C$3,825.87
Overhead (14%)C$14,162.60
Profit (11%)C$10,857.99
Cost / m²
LaborC$363.54
MaterialsC$140.80
EquipmentC$25.51
OverheadC$94.42
ProfitC$72.39
Grand TotalC$670.26
Materials / Labor
0.39
Direct Cost %
93.9%
30 work items across 7 categories, 83 resources

Cost Flow

7iVisual flow of the total budget through work categories, showing proportional cost distribution
Total CostC$100,539.52Finishes: C$20,990.79 (20.9%)MEP — HVAC: C$7,188.12 (7.1%)MEP — Plumbing: C$33,845.13 (33.7%)MEP — Electrical: C$20,246.42 (20.1%)Partitions & Doors: C$21,671.52 (21.6%)Reception & Furniture: C$14,637.66 (14.6%)Demolition & Preparation: C$858.37 (0.9%)Finishes20.9%MEP — HVAC7.1%MEP — Plumbing33.7%MEP — Electrical20.1%Partitions & Doors21.6%Reception & Furniture14.6%Demolition & Preparation0.9%
  • Complete BOQ: 34 work items for Medical Clinic / Dental Practice Fit-Out
  • 3 work item(s) not found in pricing DB for language 'en'.

Categories

7iCost distribution by work category — earthwork, structure, facade, MEP, finishes, etc.
CategoryCostCost / m²Share
FinishesC$20,990.79C$139.9420.9%
MEP — HVACC$7,188.12C$47.927.1%
MEP — PlumbingC$33,845.13C$225.6333.7%
MEP — ElectricalC$20,246.42C$134.9820.1%
Partitions & DoorsC$21,671.52C$144.4821.6%
Reception & FurnitureC$14,637.66C$97.5814.6%
Demolition & PreparationC$858.37C$5.720.9%

Top Items

DescriptionTotal
Installation of partitions made of plasterboard sheets …C$13,411.68
Flour sifter, type: P3-BRB, number of receptions 6C$9,179.47
Covering walls with glass wallpaper painted with polyvi…C$8,686.54
Installation of a single-level frame for a suspended ce…C$8,675.83
IKM-15 equipment: intermediate station for one systemC$8,430.72

What-If Scenarios

iExplore how changes in material, labor, or equipment costs affect the total project budget
Optimistic (-10%)
C$90,485.57
↓ C$10,053.95 savings
Labor -10% · Materials -10% · Equipment -10%
Base Estimate
C$100,539.52
Deterministic
Labor ×1.00 · Materials ×1.00 · Equipment ×1.00
Pessimistic (+15%)
C$115,620.45
↑ C$15,080.93 increase
Labor +15% · Materials +15% · Equipment +15%
Custom Scenario: Adjust cost components
Labor 0%
Materials 0%
Equipment 0%
Custom Scenario Total Cost
C$100,539.52

Project Schedule

≈6 monthsiProject timeline with critical path method (CPM), Gantt chart, and resource allocation
Construction PhasesAI
Site PreparationSite clearing, survey, temporary facilities, utilities disconnection73d
Earthwork and ExcavationBulk excavation, grading, soil stabilization, utility trenches8d
Foundation and UndergroundFoundation excavation, formwork, reinforcement, concrete pouring, basement construction8d
Structural FrameworkConcrete frame, steel structure, floor slabs, structural elements8d
Roofing SystemRoof structure, waterproofing, insulation, drainage systems8d
External Walls and FacadeExterior walls, cladding, insulation, weather barriers8d
Windows and External DoorsWindow installation, external door frames, glazing, sealing8d
MEP Rough-in InstallationElectrical rough-in, plumbing rough-in, HVAC ductwork, medical gas systems8d
Medical InfrastructureMedical gas systems, nurse call systems, emergency power, specialized equipment prep8d
Interior PartitionsNon-load bearing walls, door frames, interior wall construction8d
Insulation and DrywallThermal insulation, sound insulation, drywall installation, taping8d
Ceiling SystemsSuspended ceilings, acoustic panels, ceiling-mounted fixtures prep8d
Interior DoorsInterior door installation, hardware, access control prep8d
Flooring InstallationMedical-grade flooring, vinyl, ceramic tiles, specialty hospital flooring8d
MEP Trim-out and FixturesElectrical fixtures, plumbing fixtures, HVAC grilles, medical equipment connections8d
Painting and Wall FinishesPrime and paint walls, specialty hospital finishes, wall protection8d
Medical Equipment InstallationMedical equipment installation, testing, calibration, specialized systems8d
Commissioning and TestingSystem commissioning, performance testing, safety systems verification, inspections8d
Final Cleanup and HandoverDeep cleaning, final inspections, documentation handover, occupancy permit8d
6
months
193
days
19
phases
16
Critical Path
6
Peak workers
1,939
Labor Hours
M1 M2 M3 M4 M5 M6 M7 Crew/Float Site Preparation Site Preparation: 73d, Crew 5, Float 0d 73d 5 / - Earthwork and Excavat… Earthwork and Excavation: 8d, Crew 2, Float 0d 2 / - Foundation and Underg… Foundation and Underground: 8d, Crew 2, Float 0d 2 / - Structural Framework Structural Framework: 8d, Crew 2, Float 0d 2 / - Roofing System Roofing System: 8d, Crew 2, Float 3d 2 / 3d External Walls and Fa… External Walls and Facade: 8d, Crew 2, Float 0d 2 / - Windows and External … Windows and External Doors: 8d, Crew 2, Float 0d 2 / - MEP Rough-in Installa… MEP Rough-in Installation: 8d, Crew 2, Float 3d 2 / 3d Medical Infrastructure Medical Infrastructure: 8d, Crew 2, Float 76d 2 / 76d Interior Partitions Interior Partitions: 8d, Crew 2, Float 0d 2 / - Insulation and Drywall Insulation and Drywall: 8d, Crew 2, Float 0d 2 / - Ceiling Systems Ceiling Systems: 8d, Crew 2, Float 0d 2 / - Interior Doors Interior Doors: 8d, Crew 2, Float 0d 2 / - Flooring Installation Flooring Installation: 8d, Crew 2, Float 0d 2 / - MEP Trim-out and Fixt… MEP Trim-out and Fixtures: 8d, Crew 2, Float 0d 2 / - Painting and Wall Fin… Painting and Wall Finishes: 8d, Crew 2, Float 0d 2 / - Medical Equipment Ins… Medical Equipment Installation: 8d, Crew 2, Float 0d 2 / - Commissioning and Tes… Commissioning and Testing: 8d, Crew 2, Float 0d 2 / - Final Cleanup and Han… Final Cleanup and Handover: 8d, Crew 2, Float 0d 2 / - Workers 101K 50% (36d)
Site PreparationEarthwork and ExcavationFoundation and UndergroundStructural FrameworkRoofing SystemExternal Walls and FacadeWindows and External DoorsMEP Rough-in InstallationMedical InfrastructureInterior PartitionsInsulation and DrywallCeiling SystemsInterior DoorsFlooring InstallationMEP Trim-out and FixturesPainting and Wall FinishesMedical Equipment InstallationCommissioning and TestingFinal Cleanup and HandoverCumulative Cost
Labor Hours by Phase
Site Preparation
1,939 hours
Earthwork and Excava
50 hours
Foundation and Under
50 hours
Structural Framework
50 hours
Roofing System
50 hours
External Walls and F
50 hours
Windows and External
50 hours
MEP Rough-in Install
50 hours
Medical Infrastructu
50 hours
Interior Partitions
50 hours
Insulation and Drywa
50 hours
Ceiling Systems
50 hours
Interior Doors
50 hours
Flooring Installatio
50 hours
MEP Trim-out and Fix
50 hours
Painting and Wall Fi
50 hours
Medical Equipment In
50 hours
Commissioning and Te
50 hours
Final Cleanup and Ha
50 hours

Monthly Cash Flow

3 monthsiMonthly cost distribution and cumulative S-curve showing how project spending builds over time
41%
M1
82%
M2
100%
M3
MonthdaysMonthly Cost%Cumulative%
M11–30C$41,317.6141.1%C$41,317.6141%
M231–60C$41,317.6141.1%C$82,635.2282%
M361–90C$17,904.3017.8%C$100,539.52100%

Daily Cash Flow

11 weeks
1%
D1
11%
D8
21%
D15
30%
D22
40%
D29
49%
D36
59%
D43
68%
D50
78%
D57
88%
D64
97%
D71
100%
D73
WeekdaysWeekly Cost%Cumulative%
W1D1–D7C$9,640.789.6%C$9,640.7810%
W2D8–D14C$9,640.789.6%C$19,281.5519%
W3D15–D21C$9,640.789.6%C$28,922.3329%
W4D22–D28C$9,640.789.6%C$38,563.1038%
W5D29–D35C$9,640.789.6%C$48,203.8848%
W6D36–D42C$9,640.789.6%C$57,844.6658%
W7D43–D49C$9,640.789.6%C$67,485.4367%
W8D50–D56C$9,640.789.6%C$77,126.2177%
W9D57–D63C$9,640.789.6%C$86,766.9886%
W10D64–D70C$9,640.789.6%C$96,407.7696%
W11D71–D73C$4,131.764.1%C$100,539.52100%

Line Items

30 itemsiDetailed work items grouped by category with quantities, unit prices, and resource breakdown
Demolition & Preparation 1 items C$858.37
#CodeDescriptionQtyUnitUnit PriceTotal
1KAME_KARI_MEKADX_KAME
Stump removal of stumps and wood debris hidden in the upper layers of peat deposits using rotary stump grinders on a 59
6.0
6 m³(Demolition & Preparation)
haC$113.09C$858.37
C$678.56 +15% C$101.78 +10% C$78.03
Labor Materials Equipment
TypeResourceQtyUnitUnit PriceCost
Bulldozers, power 59 kW (80 hp)11.88Machine hoursC$37.65C$447.25
Personnel: 1 person-hour/machine-hour11.88Machine hoursC$12.74C$151.31
Rotary harvesters (without tractor)11.88Machine hoursC$6.73C$80.00
Partitions & Doors 3 items C$21,671.52
#CodeDescriptionQtyUnitUnit PriceTotal
2MEKA_KASA_KAKAPU_KAME
Installation of partitions made of plasterboard sheets (drywall) with a double metal frame and two-layer cladding on bot
100.0
100 m²(Partitions & Doors)
m2C$106.02C$13,411.68
C$10,602.11 +15% C$1,590.32 +10% C$1,219.24
Labor Materials Equipment
TypeResourceQtyUnitUnit PriceCost
Worker Category 1182.00hrsC$34.89C$6,349.88
Water0.13m3C$2.57C$0.33
Electricity3.95kWhC$0.42C$1.66
Elastic self-adhesive tapes for guide profiles 50x30000 mm267.00mC$0.46C$124.03
Perforated paper reinforcement tapes for increasing the crack resistance of joints, width 52 mm152.00mC$0.15C$23.54
Paper tapes for creating artificial cracks between frame structures and adjacent surfaces, with an adhesive layer on one side and an anti-adhesive coating on the other, white, width 65 mm1.77100 mC$184.51C$326.58
Plastic dowels with screws, diameter 6 mm, length 35 mm, screw diameter TO.SA mm, screw length 50 mm3.38100 pcsC$4.29C$14.51
Self-tapping steel screws, oxidized, with countersunk head and cross-shaped slot, pointed, diameter TO.SA mm, length 25 mm13.53100 pcsC$1.68C$22.75
Self-tapping steel screws, oxidized, with countersunk head and cross-shaped slot, pointed, diameter TO.SA mm, length 35 mm35.33100 pcsC$2.19C$77.37
Galvanized steel guide profile for installing gypsum partitions and suspended ceilings, dimensions 50x40 mm, steel thickness KA.NE mm151.00mC$3.85C$581.20
Galvanized steel rack profile, dimensions 50x50 mm, thickness KA.NE mm407.00mC$6.08C$2,475.88
Deep-penetrating, quick-drying, vapor-permeable strengthening primer20.00kgC$6.57C$131.40
Dry putty mixes based on high-strength gypsum with polymer additives, aggregate size no more than KA.MESA mm, flexural strength RI.LI MPa21.00kgC$5.77C$121.24
Universal dry putty mixtures based on gypsum with polymer additives, aggregate size not exceeding KA.RI mm, flexural strength not less than ME.KA MPa149.00kgC$1.50C$224.13
Mobile cranes, lifting capacity 16 t0.91Machine hoursC$91.44C$83.22
Personnel: 1 person-hour/machine-hour0.91Machine hoursC$26.34C$23.96
Flatbed trucks, load capacity up to 5 tons0.37Machine hoursC$35.51C$13.14
Personnel: 1 person-hour/machine-hour0.37Machine hoursC$19.60C$7.25
Electric shears0.21Machine hoursC$0.20C$0.04
3SANE_KAME_KARIVO_KATOReplacing door panels: made of solid wood fiberboard6.0
6 pcs(Partitions & Doors)
pcsC$163.26C$1,239.18
C$979.59 +15% C$146.94 +10% C$112.65
Labor Materials Equipment
TypeResourceQtyUnitUnit PriceCost
Worker Category 138.46hrsC$25.37C$975.88
Self-tapping steel screws with a semi-circular head and a straight slot, pointed, diameter TO.SA mm, length 30-35 mm0.07kgC$6.05C$0.44
Dry wood glue0.60kgC$5.45C$3.27
4RIDX_KARI_KALIME_KAME
Installation of a stainless steel "metro" type swing door for the entrance group with a floor closer for doors weighing
1.0
1 pcs(Partitions & Doors)
pcsC$5,549.93C$7,020.66
C$5,549.93 +15% C$832.49 +10% C$638.24
Labor Materials Equipment
TypeResourceQtyUnitUnit PriceCost
Worker Category 19.56hrsC$25.07C$239.71
Floor door closer with spindle for swing doors up to 1400 mm wide, door weight up to 300 kg1.00pcsC$1,347.18C$1,347.18
Single-leaf swing (pendulum) door for the metro with accessories, stainless steel profile, filled with VO.PU mm thick tempered laminated glass, dimensions 2195x933x55 mm1.00setC$3,959.29C$3,959.29
Mobile cranes, lifting capacity 16 t0.02Machine hoursC$66.10C$1.33
Personnel: 1 person-hour/machine-hour0.02Machine hoursC$19.16C$0.38
Flatbed trucks, load capacity up to 10 tons0.04Machine hoursC$36.85C$1.47
Personnel: 1 person-hour/machine-hour0.04Machine hoursC$14.26C$0.57
Finishes 6 items C$20,990.79
#CodeDescriptionQtyUnitUnit PriceTotal
5SALI_KAME_KAKADX_KAMERepair of polyvinyl chloride tile flooring: 200x200 mm120.0
120 m²(Finishes)
pcsC$1.96C$297.18
C$234.92 +15% C$35.24 +10% C$27.02
Labor Materials Equipment
TypeResourceQtyUnitUnit PriceCost
Worker Category 15.42hrsC$24.44C$132.57
PVC floor tiles, thickness ME.RI mm4.80m2C$16.23C$77.91
KN-2 rubber adhesive mastic2.17kgC$8.26C$17.93
Single-mast hoists, load capacity up to 500 kg, lifting height 45 m0.12Machine hoursC$2.34C$0.28
Personnel: 1 person-hour/machine-hour0.12Machine hoursC$12.50C$1.50
Flatbed trucks, load capacity up to 5 tons0.12Machine hoursC$25.37C$3.04
Personnel: 1 person-hour/machine-hour0.12Machine hoursC$14.06C$1.69
6MEME_KAME_KARILI_KAPU
Installation of cement mortar tile coverings: ceramic carpet tiles, 4-6 mm thick
30.0
30 m²(Finishes)
m2C$64.26C$2,438.55
C$1,927.70 +15% C$289.16 +10% C$221.69
Labor Materials Equipment
TypeResourceQtyUnitUnit PriceCost
Worker Category 126.51hrsC$23.33C$618.45
Water1.16m3C$1.81C$2.09
Wood shavings0.92m3C$73.73C$67.68
Ready-mixed masonry mortar, cement, M2000.66m3C$220.92C$145.80
Carpets made of unglazed ceramic tiles for flooring, smooth, colored, thickness 4-6 mm30.30m2C$35.34C$1,070.89
Universal front-end pneumatic wheeled single-bucket loaders, nominal capacity of main bucket RI.NE m3, load capacity 5 t0.11Machine hoursC$68.22C$7.37
Personnel: 1 person-hour/machine-hour0.11Machine hoursC$16.29C$1.76
Single-mast hoists, load capacity up to 500 kg, lifting height 45 m0.75Machine hoursC$2.36C$1.76
Personnel: 1 person-hour/machine-hour0.75Machine hoursC$12.59C$9.41
Flatbed trucks, load capacity up to 5 tons0.06Machine hoursC$25.53C$1.61
Personnel: 1 person-hour/machine-hour0.06Machine hoursC$14.17C$0.89
7MESA_KAME_KAMEDX_KADX
Installation of border and frieze ceramic tiles when tiling walls on brick and concrete: on mortar
20.0
20 m²(Finishes)
mC$22.97C$581.07
C$459.35 +15% C$68.90 +10% C$52.82
Labor Materials Equipment
TypeResourceQtyUnitUnit PriceCost
2nd grade worker0.16hrsC$21.89C$3.59
Grade 3 worker0.24hrsC$23.90C$5.74
Grade 4 worker3.45hrsC$26.92C$92.88
Electricity0.08kWhC$2,272.96C$213.62
Colored cotton rags0.00kgC$28,594.00C$142.42
Single-mast hoists, load capacity up to 500 kg, lifting height 45 m0.00Machine hoursC$2.36C$0.01
Personnel: 1 person-hour/machine-hour0.00Machine hoursC$12.69C$0.05
Flatbed trucks, load capacity up to 5 tons0.03Machine hoursC$25.62C$0.67
Personnel: 1 person-hour/machine-hour0.03Machine hoursC$14.28C$0.37
8MESA_KANE_KAKALI_KAME
Covering walls with glass wallpaper painted with polyvinyl acetate paints in one go: with preparation
200.0
200 m²(Finishes)
m2C$34.33C$8,686.54
C$6,866.83 +15% C$1,030.02 +10% C$789.69
Labor Materials Equipment
TypeResourceQtyUnitUnit PriceCost
Worker Category 1213.78hrsC$27.17C$5,808.44
Water0.06m3C$23.37C$1.44
Electricity0.24kWhC$3.83C$0.96
Sanding paper0.80m2C$159.55C$127.69
Colored cotton rags0.02kgC$48.15C$0.96
Deep penetration primer composition20.00kgC$45.53C$910.59
Single-mast hoists, load capacity up to 500 kg, lifting height 45 m0.04Machine hoursC$2.40C$0.09
Personnel: 1 person-hour/machine-hour0.04Machine hoursC$12.81C$0.51
Flatbed trucks, load capacity up to 5 tons0.40Machine hoursC$25.99C$10.40
Personnel: 1 person-hour/machine-hour0.40Machine hoursC$14.41C$5.76
9MESA_KAME_KASADX_KAME
Installation of a single-level frame for a suspended ceiling in clean rooms
150.0
150 m²(Finishes)
m2C$45.72C$8,675.83
C$6,858.36 +15% C$1,028.75 +10% C$788.71
Labor Materials Equipment
TypeResourceQtyUnitUnit PriceCost
Grade 1 worker0.01hrsC$33.56C$0.50
2nd grade worker0.12hrsC$36.58C$4.40
Grade 5 worker20.93hrsC$51.69C$1,081.71
Grade 6 worker20.93hrsC$60.42C$1,264.29
Electricity7.00kWhC$0.49C$3.42
Polypropylene anchor dowel nails with flange, diameter 6 mm, length 40 mm1.51100 pcsC$15.36C$23.26
Galvanized steel ceiling profile suspension comb (stringer), steel thickness KA.NE mm216.00mC$20.70C$4,470.97
Mobile cranes, lifting capacity 16 t0.03Machine hoursC$111.00C$3.32
Personnel: 1 person-hour/machine-hour0.03Machine hoursC$32.06C$0.95
Single-mast hoists, load capacity up to 500 kg, lifting height 45 m0.01Machine hoursC$3.98C$0.06
Personnel: 1 person-hour/machine-hour0.01Machine hoursC$21.21C$0.31
Flatbed trucks, load capacity up to 10 tons0.06Machine hoursC$61.89C$3.71
Personnel: 1 person-hour/machine-hour0.06Machine hoursC$23.86C$1.44
10MEME_KAME_KAPUKA_KARI
Installation of polyvinyl chloride skirting boards: on KN-3 coumarone-rubber mastic
60.0
60 m(Finishes)
mC$4.11C$311.62
C$246.34 +15% C$36.95 +10% C$28.33
Labor Materials Equipment
TypeResourceQtyUnitUnit PriceCost
Worker Category 15.41hrsC$28.83C$155.85
KN-3 rubber adhesive mastic0.01tC$14,955.41C$89.72
Flatbed trucks, load capacity up to 5 tons0.02Machine hoursC$27.51C$0.50
Personnel: 1 person-hour/machine-hour0.02Machine hoursC$15.07C$0.27
MEP — Electrical 6 items C$20,246.42
#CodeDescriptionQtyUnitUnit PriceTotal
11KAVO_KATO_SADXDX_MERIm
Lighting panels installed on the wall: bolts on the structure, shield weight up to 6 kg
24.0
24 pcs(MEP — Electrical)
pcsC$95.22C$2,890.97
C$2,285.35 +15% C$342.80 +10% C$262.82
Labor Materials Equipment
TypeResourceQtyUnitUnit PriceCost
Worker Category 165.52hrsC$27.53C$1,803.98
Rubberized cotton insulating tape for electrical installation and repair work, black, width 20 mm, thickness KA.TOSA mm46.08mC$0.25C$11.52
Polypropylene expansion anchors0.96100 pcsC$2.19C$2.10
MA-0115 oil paint, mummy, iron minium4.80kgC$5.12C$24.59
Flexible jumpers, type PGS-502.4010 pcsC$53.38C$128.11
Insulating bushings, dimensions 65x50x18 mm0.481000 pcsC$206.74C$99.24
U731M type clamps for main and branch wires and cables0.96100 pcsC$102.47C$98.37
Polyvinyl chloride electrical conduit, wall thickness KA.NE mm3.36kgC$10.68C$35.90
Mobile cranes, lifting capacity 16 t0.72Machine hoursC$65.83C$47.39
Personnel: 1 person-hour/machine-hour0.72Machine hoursC$19.05C$13.72
Flatbed trucks, load capacity up to 5 tons0.48Machine hoursC$25.57C$12.27
Personnel: 1 person-hour/machine-hour0.48Machine hoursC$14.18C$6.80
Welding machines for manual arc welding, welding current up to 350 A0.96Machine hoursC$1.42C$1.37
12TOPU_KAME_KALIME_KAMEm
Stationary lamp: with emergency power supply, with adjustable lighting, six-reflector
8.0
8 pcs(MEP — Electrical)
pcsC$803.32C$8,129.58
C$6,426.55 +15% C$963.98 +10% C$739.05
Labor Materials Equipment
TypeResourceQtyUnitUnit PriceCost
Worker Category 1247.20hrsC$25.98C$6,421.30
Electricity17.60kWhC$0.30C$5.25
13KAVO_KATO_SADXME_KAVOmPlug socket: non-recessed type with exposed wiring30.0
30 pcs(MEP — Electrical)
pcsC$9.68C$367.21
C$290.29 +15% C$43.54 +10% C$33.38
Labor Materials Equipment
TypeResourceQtyUnitUnit PriceCost
Worker Category 110.37hrsC$27.75C$287.72
Electricity0.64kWhC$0.30C$0.19
Rubberized cotton insulating tape for electrical installation and repair work, black, width 20 mm, thickness KA.TOSA mm2.75mC$0.25C$0.70
Polypropylene expansion anchors0.31100 pcsC$2.21C$0.68
Mobile cranes, lifting capacity 16 t0.01Machine hoursC$66.45C$0.60
Personnel: 1 person-hour/machine-hour0.01Machine hoursC$19.20C$0.17
Flatbed trucks, load capacity up to 5 tons0.01Machine hoursC$25.81C$0.16
Personnel: 1 person-hour/machine-hour0.01Machine hoursC$14.29C$0.08
14MEKA_KAME_KARISA_KATOmIKM-15 equipment: intermediate station for one system8.0
8 pcs(MEP — Electrical)
pcsC$833.08C$8,430.72
C$6,664.60 +15% C$999.69 +10% C$766.43
Labor Materials Equipment
TypeResourceQtyUnitUnit PriceCost
Worker Category 1224.00hrsC$26.25C$5,879.91
Electric winches with a pulling force of up to SA.LIDX kN (KA.SADX t)97.60Machine hoursC$0.41C$39.82
Universal front-end pneumatic wheeled single-bucket loaders, nominal capacity of main bucket RI.NE m3, load capacity 5 t8.80Machine hoursC$68.64C$604.00
Personnel: 1 person-hour/machine-hour8.80Machine hoursC$16.01C$140.87
15KARI_KATO_KAKAME_KASA
For each additional/excluded database out of ten recorded, add/exclude from norm KARI-KATO-KAKAME-KAME
15.0
15 pcs(MEP — Electrical)
pcsC$16.61C$315.25
C$249.20 +15% C$37.38 +10% C$28.66
Labor Materials Equipment
TypeResourceQtyUnitUnit PriceCost
Lead engineer5.25person-hourC$18.99C$99.68
For each additional/excluded database out of ten recorded, add/exclude from norm15.00pcsC$7.48C$112.14
For each additional/excluded database out of ten recorded, add/exclude from norm15.00pcsC$2.49C$37.38
16MEKA_MEKA_KAMEKA_KARIm
Configuration of facility equipment for the hardware and software complex of the notification transmission system for jo
1.0
1 set(MEP — Electrical)
setC$89.08C$112.69
C$89.08 +15% C$13.36 +10% C$10.24
Labor Materials Equipment
TypeResourceQtyUnitUnit PriceCost
Grade 5 worker0.46hrsC$31.19C$14.34
Grade 6 worker2.05hrsC$36.46C$74.74
MEP — HVAC 3 items C$7,188.12
#CodeDescriptionQtyUnitUnit PriceTotal
17TOPU_KARI_KAKAPU_RIRImVentilation system for sterile filling room1.0
1 set(MEP — HVAC)
pcsC$1,994.67C$2,523.26
C$1,994.67 +15% C$299.20 +10% C$229.39
Labor Materials Equipment
TypeResourceQtyUnitUnit PriceCost
Worker Category 144.90hrsC$30.92C$1,388.24
Electricity1,164.00kWhC$0.29C$336.19
Mobile cranes, lifting capacity 16 t2.46Machine hoursC$64.07C$157.62
Personnel: 1 person-hour/machine-hour2.46Machine hoursC$18.55C$45.62
General-purpose electric hoists, load capacity 1 t1.45Machine hoursC$0.32C$0.46
Flatbed trucks, load capacity up to 5 tons1.72Machine hoursC$24.88C$42.80
Personnel: 1 person-hour/machine-hour1.72Machine hoursC$13.80C$23.74
18KATO_KAME_KANESA_KAME
Process control or protection unit for temperature, relative humidity, pressure, or flow rate parameters
6.0
6 pcs(MEP — HVAC)
unitC$401.21C$3,045.20
C$2,407.27 +15% C$361.09 +10% C$276.84
Labor Materials Equipment
TypeResourceQtyUnitUnit PriceCost
Grade 6 worker18.96hrsC$36.43C$690.64
Category I technician12.66person-hourC$28.74C$363.87
Category I engineer12.66person-hourC$43.51C$550.82
Category II Engineer12.66person-hourC$39.67C$502.28
Lead engineer6.30person-hourC$47.56C$299.66
19KATO_KARI_KAKADX_KAMECOMLocal exhaust or shelter during air extraction: in one place4.0
4 pcs(MEP — HVAC)
pcsC$320.09C$1,619.66
C$1,280.36 +15% C$192.05 +10% C$147.24
Labor Materials Equipment
TypeResourceQtyUnitUnit PriceCost
Category I technician13.84person-hourC$7.04C$97.41
Category I engineer8.64person-hourC$10.65C$92.06
Category II Engineer8.64person-hourC$9.72C$83.94
Lead engineer3.44person-hourC$11.65C$40.07
Local exhaust or shelter during air extraction: in one place4.00pcsC$241.72C$966.88
MEP — Plumbing 5 items C$14,946.64
#CodeDescriptionQtyUnitUnit PriceTotal
20NESA_KAME_KAKANE_MENEReplacement: two-compartment sinks5.0
5 pcs(MEP — Plumbing)
pcsC$314.54C$1,989.48
C$1,572.71 +15% C$235.91 +10% C$180.86
Labor Materials Equipment
TypeResourceQtyUnitUnit PriceCost
Worker Category 116.75hrsC$26.14C$437.80
Cable0.00tC$205,661.92C$102.92
Dowels0.00tC$183,883.42C$91.95
Self-tapping steel screws, oxidized, with countersunk head and cross-shaped slot, pointed, diameter 8 mm, length 100 mm0.00tC$117,592.44C$58.84
Expanding gypsum-clay cement0.00tC$38,448.44C$19.15
Polyvinyl chloride bushings0.20100 pcsC$4,297.18C$859.48
Single-mast hoists, load capacity up to 500 kg, lifting height 45 m0.04Machine hoursC$2.46C$0.11
Personnel: 1 person-hour/machine-hour0.04Machine hoursC$13.05C$0.59
Flatbed trucks, load capacity up to 5 tons0.04Machine hoursC$26.69C$1.20
Personnel: 1 person-hour/machine-hour0.04Machine hoursC$14.69C$0.66
21NESA_KAME_KAKANE_MENEReplacement: two-compartment sinks1.0
1 pcs(MEP — Plumbing)
pcsC$314.54C$397.90
C$314.54 +15% C$47.18 +10% C$36.17
Labor Materials Equipment
TypeResourceQtyUnitUnit PriceCost
Worker Category 13.35hrsC$26.14C$87.56
Cable0.00tC$205,734.40C$20.55
Dowels0.00tC$183,948.23C$18.36
Self-tapping steel screws, oxidized, with countersunk head and cross-shaped slot, pointed, diameter 8 mm, length 100 mm0.00tC$117,633.88C$11.77
Expanding gypsum-clay cement0.00tC$38,461.99C$3.79
Polyvinyl chloride bushings0.04100 pcsC$4,298.70C$172.00
Single-mast hoists, load capacity up to 500 kg, lifting height 45 m0.01Machine hoursC$2.44C$0.02
Personnel: 1 person-hour/machine-hour0.01Machine hoursC$13.05C$0.12
Flatbed trucks, load capacity up to 5 tons0.01Machine hoursC$26.49C$0.24
Personnel: 1 person-hour/machine-hour0.01Machine hoursC$14.69C$0.13
22MEVO_KARI_KAKANE_KAPU
Installation of plate heat exchangers for heating and hot water supply systems with a mass of: over 200 to 300 kg
4.0
4 pcs(MEP — Plumbing)
pcsC$1,165.46C$5,897.23
C$4,661.84 +15% C$699.28 +10% C$536.11
Labor Materials Equipment
TypeResourceQtyUnitUnit PriceCost
Worker Category 1116.52hrsC$27.07C$3,154.48
Water6.40m3C$76.99C$492.56
Electricity0.36kWhC$12.61C$4.34
Plastic dowels, diameter 14 mm, length 70 mm0.16100 pcsC$378.96C$60.83
Rubber gaskets (pressed technical plate)2.00kgC$404.18C$808.56
Colored cotton rags0.16kgC$158.62C$25.28
Mobile cranes, lifting capacity 16 t0.52Machine hoursC$67.11C$34.90
Personnel: 1 person-hour/machine-hour0.52Machine hoursC$19.29C$10.03
Electric winches with a pulling force of up to SA.LIDX kN (KA.SADX t)7.20Machine hoursC$0.41C$2.98
Filling and pressure testing units, flow rate up to 70 m3/h0.56Machine hoursC$75.50C$42.28
Personnel: 1 person-hour/machine-hour0.56Machine hoursC$14.36C$8.04
Flatbed trucks, load capacity up to 5 tons0.40Machine hoursC$26.06C$10.42
Personnel: 1 person-hour/machine-hour0.40Machine hoursC$14.36C$5.74
Welding machines for manual arc welding, welding current up to 350 A0.96Machine hoursC$1.45C$1.39
23METO_KAME_KATOKA_MEDXm
Individual tests: high and low pressure compressed air supply systems
1.0
1 set(MEP — Plumbing)
setC$4,970.50C$6,287.69
C$4,970.50 +15% C$745.58 +10% C$571.61
Labor Materials Equipment
TypeResourceQtyUnitUnit PriceCost
Worker Category 1177.00hrsC$28.08C$4,970.50
24MEVO_KAME_MEMEME_KARIm
Suction-type fuel dispenser with vapor recovery system: for 2 types of fuel
1.0
1 set(MEP — Plumbing)
pcsC$295.92C$374.34
C$295.92 +15% C$44.39 +10% C$34.03
Labor Materials Equipment
TypeResourceQtyUnitUnit PriceCost
Average workload TO.KA4.01hrsC$22.48C$90.12
Universal detachable connections with cap nut, straight, with internal and external thread, size 1 1/2"0.2010 pcsC$706.63C$141.33
Mobile cranes, lifting capacity 16 t0.54Machine hoursC$62.33C$33.66
Personnel: 1 person-hour/machine-hour0.54Machine hoursC$18.04C$9.74
Flatbed trucks, load capacity up to 5 tons0.56Machine hoursC$24.21C$13.55
Personnel: 1 person-hour/machine-hour0.56Machine hoursC$13.43C$7.52
Reception & Furniture 6 items C$14,637.66
#CodeDescriptionQtyUnitUnit PriceTotal
25TOKA_KAME_KARINE_KAPUmFlour sifter, type: P3-BRB, number of receptions 61.0
1 pcs(Reception & Furniture)
pcsC$7,256.50C$9,179.47
C$7,256.50 +15% C$1,088.47 +10% C$834.50
Labor Materials Equipment
TypeResourceQtyUnitUnit PriceCost
Worker Category 1239.00hrsC$28.62C$6,840.38
Industrial oil I-20A1.12lC$4.17C$4.67
Electricity84.30kWhC$0.30C$24.93
Bolts with nuts and washers for construction2.85kgC$8.53C$24.30
Galvanized steel threaded studs, thread diameter M10, length 700-1050 mm0.03tC$4,198.24C$125.94
Rubber gaskets (pressed technical plate)0.20kgC$9.48C$1.90
Mobile cranes, lifting capacity 16 t1.42Machine hoursC$65.60C$93.16
Personnel: 1 person-hour/machine-hour1.42Machine hoursC$18.99C$26.96
Electric winches with pulling force up to TOME.TODX kN (TO.RI t)1.74Machine hoursC$0.81C$1.41
Flatbed trucks, load capacity up to 5 tons1.42Machine hoursC$25.48C$36.18
Personnel: 1 person-hour/machine-hour1.42Machine hoursC$14.13C$20.06
Electric diamond drilling rigs for reinforced concrete, drilling diameter up to 250 mm3.18Machine hoursC$1.56C$4.95
Personnel: 1 person-hour/machine-hour3.18Machine hoursC$16.25C$51.67
26TOPU_KAME_KATONE_KAMEmSwivel chair10.0
10 pcs(Reception & Furniture)
pcsC$166.64C$2,108.00
C$1,666.40 +15% C$249.96 +10% C$191.64
Labor Materials Equipment
TypeResourceQtyUnitUnit PriceCost
Worker Category 162.00hrsC$26.88C$1,666.40
27TOPU_KAME_KASANE_KAMEmChair: lightweight dental3.0
3 set(Reception & Furniture)
pcsC$230.27C$873.87
C$690.81 +15% C$103.62 +10% C$79.44
Labor Materials Equipment
TypeResourceQtyUnitUnit PriceCost
Worker Category 124.60hrsC$28.08C$690.81
28KAPU_KANE_KAKARI_KARIReagent treatment of wells with a depth of: up to 400 m8.0
8 m(Reception & Furniture)
mC$232.05C$2,348.35
C$1,856.40 +15% C$278.46 +10% C$213.49
Labor Materials Equipment
TypeResourceQtyUnitUnit PriceCost
Worker Category 118.44hrsC$19.17C$353.52
Water0.75m3C$512.97C$386.88
Mobile drilling rigs for rotary drilling of wells, drilling depth up to 500 m, winch lifting capacity up to MERI.SA t5.61Machine hoursC$116.67C$654.66
Personnel: 1 person-hour/machine-hour5.61Machine hoursC$14.58C$81.81
Mobile cranes, lifting capacity 16 t0.37Machine hoursC$66.24C$24.43
Personnel: 1 person-hour/machine-hour0.37Machine hoursC$13.66C$5.04
Automated cementing units, capacity 15 m3/h0.68Machine hoursC$23.56C$16.02
Personnel: 1 person-hour/machine-hour0.68Machine hoursC$9.04C$6.15
Tank trucks, volume 8 m34.32Machine hoursC$60.74C$262.34
Personnel: 1 person-hour/machine-hour4.32Machine hoursC$10.17C$43.92
Flatbed trucks, load capacity up to 5 tons0.54Machine hoursC$25.73C$14.01
Personnel: 1 person-hour/machine-hour0.54Machine hoursC$10.17C$5.54
Pumps, capacity 150 m3/h, head 100 m, power 75 kW0.16Machine hoursC$12.98C$2.08
29KAVO_KATO_SAPUTO_KADXmRoad sign with internal lighting (three-dimensional light)1.0
1 set(Reception & Furniture)
pcsC$33.24C$42.05
C$33.24 +15% C$4.99 +10% C$3.82
Labor Materials Equipment
TypeResourceQtyUnitUnit PriceCost
Worker Category 10.95hrsC$21.64C$20.56
Galvanized steel bolts with hexagonal head and galvanized hexagonal nut, bolt and nut thread diameter M8, bolt length 16-100 mm0.15kgC$6.66C$1.00
Steel clamps0.89kgC$2.29C$2.04
Auto hydraulic lifts, lifting height 12 m0.28Machine hoursC$19.27C$5.39
Personnel: 1 person-hour/machine-hour0.28Machine hoursC$12.61C$3.53
Flatbed trucks, load capacity up to 5 tons0.02Machine hoursC$22.76C$0.46
Personnel: 1 person-hour/machine-hour0.02Machine hoursC$12.61C$0.26
30MEKA_MEKA_KAKANE_KAMEmAccess control system with automatic locking device1.0
1 set(Reception & Furniture)
pcsC$67.92C$85.92
C$67.92 +15% C$10.19 +10% C$7.81
Labor Materials Equipment
TypeResourceQtyUnitUnit PriceCost
Worker Category 12.28hrsC$29.69C$67.70
Electricity0.76kWhC$0.29C$0.22
Cost Summary
Direct Cost94%C$94,417.36
Overhead+15%C$14,162.60
Profit+10%C$10,857.99
Grand TotalC$100,539.52

Resource Summary

83 resourcesiAggregated materials, labor, and equipment needed for the entire project
Materials to Order (49)
ResourceUnitQtyUnit PriceCost
Galvanized steel ceiling profile suspension comb (stringer), steel thim216.00C$20.70C$4,470.97
Single-leaf swing (pendulum) door for the metro with accessories, staiset1.00C$3,959.29C$3,959.29
Galvanized steel rack profile, dimensions 50x50 mm, thickness KA.NE mmm407.00C$6.08C$2,475.88
Floor door closer with spindle for swing doors up to 1400 mm wide, doopcs1.00C$1,347.18C$1,347.18
Carpets made of unglazed ceramic tiles for flooring, smooth, colored, m230.30C$35.34C$1,070.89
Polyvinyl chloride bushings100 pcs0.24C$4,297.83C$1,031.48
Deep penetration primer compositionkg20.00C$45.53C$910.59
Waterm38.50C$103.93C$883.30
Rubber gaskets (pressed technical plate)kg2.20C$368.39C$810.46
ElectricitykWh1,278.94C$0.46C$590.78
Galvanized steel guide profile for installing gypsum partitions and sum151.00C$3.85C$581.20
Paper tapes for creating artificial cracks between frame structures an100 m1.77C$184.51C$326.58
Universal dry putty mixtures based on gypsum with polymer additives, akg149.00C$1.50C$224.13
Colored cotton ragskg0.18C$916.63C$168.66
Ready-mixed masonry mortar, cement, M200m30.66C$220.91C$145.80
Universal detachable connections with cap nut, straight, with internal10 pcs0.20C$706.65C$141.33
Deep-penetrating, quick-drying, vapor-permeable strengthening primerkg20.00C$6.57C$131.40
Flexible jumpers, type PGS-5010 pcs2.40C$53.38C$128.11
Sanding paperm20.80C$159.61C$127.69
Galvanized steel threaded studs, thread diameter M10, length 700-1050 t0.03C$4,198.00C$125.94
Elastic self-adhesive tapes for guide profiles 50x30000 mmm267.00C$0.46C$124.03
Cablet0.00C$205,783.33C$123.47
Dry putty mixes based on high-strength gypsum with polymer additives, kg21.00C$5.77C$121.24
For each additional/excluded database out of ten recorded, add/excludepcs15.00C$7.48C$112.14
Dowelst0.00C$183,850.00C$110.31
Insulating bushings, dimensions 65x50x18 mm1000 pcs0.48C$206.75C$99.24
U731M type clamps for main and branch wires and cables100 pcs0.96C$102.47C$98.37
KN-3 rubber adhesive mastict0.01C$14,953.33C$89.72
PVC floor tiles, thickness ME.RI mmm24.80C$16.23C$77.91
Self-tapping steel screws, oxidized, with countersunk head and cross-s100 pcs35.33C$2.19C$77.37
Grand TotalC$21,120.72
Labor Requirements (13)
ResourceUnitQtyUnit PriceCost
Worker Category 1hrs1,734.02C$27.88C$48,351.64
Grade 6 workerhrs41.94C$48.40C$2,029.67
Grade 5 workerhrs21.39C$51.25C$1,096.05
Personnel: 1 person-hour/machine-hourMachine hours49.70C$14.63C$726.89
Category I engineerperson-hour21.30C$30.18C$642.88
Category II Engineerperson-hour21.30C$27.52C$586.22
Category I technicianperson-hour26.50C$17.41C$461.28
Lead engineerperson-hour14.99C$29.31C$439.41
Grade 4 workerhrs3.45C$26.92C$92.88
Average workload TO.KAhrs4.01C$22.47C$90.12
2nd grade workerhrs0.28C$28.13C$7.99
Grade 3 workerhrs0.24C$23.92C$5.74
Grade 1 workerhrs0.01C$33.33C$0.50
Grand TotalC$54,531.27
Equipment Requirements (21)
ResourceUnitQtyUnit PriceCost
Local exhaust or shelter during air extraction: in one placepcs4.00C$241.72C$966.88
Mobile drilling rigs for rotary drilling of wells, drilling depth up tMachine hours5.61C$116.67C$654.66
Universal front-end pneumatic wheeled single-bucket loaders, nominal cMachine hours8.91C$68.63C$611.37
Mobile cranes, lifting capacity 16 tMachine hours7.00C$68.54C$479.63
Bulldozers, power 59 kW (80 hp)Machine hours11.88C$37.65C$447.25
Tank trucks, volume 8 m3Machine hours4.32C$60.74C$262.34
Flatbed trucks, load capacity up to 5 tonsMachine hours6.20C$25.90C$160.65
Rotary harvesters (without tractor)Machine hours11.88C$6.73C$80.00
Electric winches with a pulling force of up to SA.LIDX kN (KA.SADX t)Machine hours104.80C$0.41C$42.80
Filling and pressure testing units, flow rate up to 70 m3/hMachine hours0.56C$75.50C$42.28
For each additional/excluded database out of ten recorded, add/excludepcs15.00C$2.49C$37.38
Automated cementing units, capacity 15 m3/hMachine hours0.68C$23.56C$16.02
Auto hydraulic lifts, lifting height 12 mMachine hours0.28C$19.25C$5.39
Flatbed trucks, load capacity up to 10 tonsMachine hours0.10C$51.80C$5.18
Electric diamond drilling rigs for reinforced concrete, drilling diameMachine hours3.18C$1.56C$4.95
Welding machines for manual arc welding, welding current up to 350 AMachine hours1.92C$1.44C$2.76
Single-mast hoists, load capacity up to 500 kg, lifting height 45 mMachine hours0.98C$2.38C$2.33
Pumps, capacity 150 m3/h, head 100 m, power 75 kWMachine hours0.16C$13.00C$2.08
Electric winches with pulling force up to TOME.TODX kN (TO.RI t)Machine hours1.74C$0.81C$1.41
General-purpose electric hoists, load capacity 1 tMachine hours1.45C$0.32C$0.46
Grand TotalC$3,825.86

Material Alternatives

iAlternative materials with approximate price difference. Percentages show material cost change relative to the current specification.
Installation of partitions made of plasterboard sheets C$4,124.62
Moisture-resistant+25%Fire-rated+35%Acoustic board+50%
Covering walls with glass wallpaper painted with polyviC$1,041.63
Premium paint+40%Ceramic coating+80%Eco-friendly paint+20%
Installation of border and frieze ceramic tiles when tiC$356.04
High-strength concrete+20%Lightweight concrete+15%Recycled aggregate-10%
Repair of polyvinyl chloride tile flooring: 200x200 mmC$95.84
Vinyl/LVT-35%Natural stone+100%Polished concrete-30%

Risk Analysis

Monte Carlo · 10KiMonte Carlo simulation (10,000 iterations) showing completion probability at different confidence levels
210days
P50
50% probability the project finishes within this timeframe. Median scenario based on Monte Carlo simulation.
223days
P80
80% probability — recommended planning basis. Accounts for common delays and uncertainties.
235days
P95
95% probability — conservative estimate. Covers nearly all risk scenarios including severe delays.
+30days
Buffer
Recommended time buffer to add to the deterministic schedule. Covers typical construction uncertainties.
Base Cost (P50)
C$100,539.52
Budget (P80)
C$106,490.63
Maximum (P95)
C$112,193.77
Contingency
+5.9%
Recommended cost reserve based on schedule risk analysis — C$5,951.11
Recommended Budget: C$106,490.63
Deterministic 193 days
P50 210 days
P80 223 days
P95 235 days
P50 P80 P95
Based on Monte Carlo simulation with 10,000 iterations using PERT distribution for each phase duration.
Peak: 6
1,939 man-hours
16 crit. phases

Cost Risk Analysis

Monte Carlo · 10,000 iterations

Monte Carlo simulation of construction cost uncertainty

Cost Percentiles

C$150,105.02
P10
C$151,762.46
P25
C$153,772.57
P50
C$156,372.69
P80
C$157,770.24
P90

Cumulative Probability (S-Curve)

+1.7%
Recommended Contingency (P80 − P50)
Reserve to cover likely cost overruns with 80% confidence — C$2,600.12

Top Risk Drivers

CategoryWork ItemRisk Share
MEP — PlumbingInstallation of giant arrays on river transport fa
43.3%
Partitions & DoorsInstallation of partitions made of plasterboard sh
11.3%
MEP — ElectricalIKM-15 equipment: intermediate station for one sys
8.8%
MEP — ElectricalStationary lamp: with emergency power supply, with
8.2%
Reception & FurnitureFlour sifter, type: P3-BRB, number of receptions 6
5.4%
MEP — PlumbingIndividual tests: high and low pressure compressed
4.8%
MEP — PlumbingInstallation of plate heat exchangers for heating
4.2%
Partitions & DoorsInstallation of a stainless steel "metro" type swi
3.1%

Sensitivity Analysis

±10%iImpact of ±10% change in each cost component on the total project cost

This tornado chart shows how a ±10% change in each cost category affects the total estimate. The wider the bar, the greater the cost impact — helping identify which cost drivers carry the most risk and where tighter cost control may be needed.

Decrease ← → IncreaseImpact
Labor54% of total
±C$5,453.13±5.4%
Materials21% of total
±C$2,112.07±2.1%
Overhead14% of total
±C$1,416.26±1.4%
Profit11% of total
±C$1,085.80±1.1%
Equipment4% of total
±C$382.59±0.4%

Cost Summary

iFinal cost breakdown with direct costs, overhead, profit, and grand total
LaborC$54,531.2654%
MaterialsC$21,120.7121%
EquipmentC$3,825.874%
Direct CostC$94,417.36
OverheadC$14,162.6014%
ProfitC$10,857.9911%
Grand TotalC$100,539.52100%
EUR equivalent€62.719,60
USD equivalent$72,284.34
GBP equivalent£54,724.73

Estimate Classification

AACE 18R-97

AACE International Recommended Practice 18R-97

2
ClassClass 2
Typical PurposeCost Control
Expected Accuracy Range: -15% / +20%
Project Definition Level: 30–75%

Cost Benchmark

Hospital · North America

Comparison of estimated cost/m² against market reference ranges

Low
3,000
▲ Typical
4,500
High
7,000
▼ Your Estimate
507 EUR/m²
Significantly below range · 0.11x ratio to typical

Methodology & Assumptions

iCalculation methodology, data sources, and key assumptions underlying this estimate
Data SourceDDC Pricing DB — English
Confidence Level50%
Overhead Rate15%
Profit Rate10%
Items Matched30
Assumptions
  • Costs adjusted by location-specific labor, material, and equipment factors
  • Exchange rates are offline reference rates and may differ from market rates
  • All amounts exclude VAT / sales tax
  • This estimate is for preliminary budgeting only — not a binding quotation
Included in Estimate
  • All labor, materials, and equipment per defined scope
  • Overhead and profit margins as specified
  • Location-adjusted pricing factors applied
Excluded from Estimate
  • VAT / sales tax
  • Permits, licenses, and legal fees
  • Temporary works and site facilities
  • Design and engineering fees
Prices current as of 2026-03-16 · No cost escalation or inflation adjustment applied

Frequently Asked Questions

How much does Medical Clinic / Dental Practice Fit-Out cost?
The cost depends on your location, materials chosen, and project scope. Use our calculator with your specific city to get an instant estimate based on 34 verified work items from our database of 55,719 construction prices.
What work items are included in this estimate?
This BOQ includes 34 work items covering Demolition & Preparation, Partitions & Doors, Finishes, MEP — Electrical, MEP — HVAC, MEP — Plumbing. Each item is matched to unit rates from our verified pricing database spanning 9 languages and 36 locations worldwide.
How long does Medical Clinic / Dental Practice Fit-Out take?
Duration depends on project size and complexity. A typical 150 m² project takes approximately 5 weeks. Our calculator generates a detailed Gantt chart with phase-by-phase scheduling.
How accurate is this estimate?
Our estimates use verified construction pricing data with location-specific adjustments (PPP factors). The Monte Carlo simulation provides P10-P90 confidence intervals. For formal budgeting, we recommend a Class 3 AACE estimate with local contractor quotes.
What does a medical clinic / dental practice fit-out include?
Detailed fit-out estimate for a 100 m² medical clinic or dental practice. Includes clinical room partitions with lead lining where required, medical gas installations, specialized ventilation, clinical lighting, vinyl flooring, reception area, sterilization room, accessible washrooms, and IT/telecom infrastructure for medical systems.

Get a Personalized Estimate for Your Project

Enter your area, city, and specific requirements to get a detailed cost estimate with local pricing, project timeline, and cost breakdown.

Calculate Cost for My Project →