Small Warehouse Construction Cost Estimate — 500 m² warehouse + 50 m² office
500 m² warehouse + 50 m² office45 work items8 sectionsToronto, Canada
About This Project
Full construction estimate for a 500 m² small warehouse or distribution facility. Covers site preparation, concrete slab-on-grade foundation, steel frame structure, insulated metal panel cladding, loading dock, industrial electrical and lighting, fire sprinkler system, and site works including parking and drainage.
Scope of Works
Site & Earthworks (4)Foundations (6)Steel Structure (5)Envelope (7)Openings (4)Office Area (50 m²) (5)MEP (9)External Works (5)
Get a Personalized Estimate for Your Project
Enter your area, city, and specific requirements to get a detailed cost estimate with local pricing, project timeline, and cost breakdown.
Data Source:DDC Pricing DB — English·55,719 items·CWICR
City Adjustment
🏛 Toronto, Canada
Your city matches the base — coefficients ×1.00
PPP Coefficients
Labor Factor
×
click to adjust
Material Factor
×
click to adjust
Equipment Factor
×
click to adjust
Prices from a professional construction database (55,719 items), adjusted to your city using construction-specific Purchasing Power Parity (PPP). Coefficients can be manually adjusted.
Detection Confidence
50%
Cost Breakdown
iHow the total cost is distributed: labor, materials, equipment, overhead, and profit margins
C$1,942,031.72Direct Cost
Labor (24%)C$118,986.82
Materials (52%)C$259,060.09
Equipment (4%)C$18,166.69
Overhead (58%)C$291,304.76
Profit (45%)C$223,333.62
Cost / m²
Labor
C$237.97
Materials
C$518.12
Equipment
C$36.33
Overhead
C$582.61
Profit
C$446.67
Grand Total
C$1,002.42
Materials / Labor
2.18
Direct Cost %
387.5%
36 work items across 8 categories, 134 resources
Cost Flow
8iVisual flow of the total budget through work categories, showing proportional cost distribution
Complete BOQ: 45 work items for Small Warehouse Construction
4 work item(s) not found in pricing DB for language 'en'.
Categories
8iCost distribution by work category — earthwork, structure, facade, MEP, finishes, etc.
Category
Cost
Cost / m²
Share
MEP
C$23,012.42
C$46.02
4.6%
Envelope
C$548,906.43
C$1,097.81
109.5%
Openings
C$5,294.50
C$10.59
1.1%
Foundations
C$1,438,395.83
C$2,876.79
287.0%
External Works
C$177,985.46
C$355.97
35.5%
Steel Structure
C$211,308.07
C$422.62
42.2%
Site & Earthworks
C$29,847.91
C$59.70
6.0%
Office Area (50 m²)
C$21,919.52
C$43.84
4.4%
Top Items
Description
Total
Wall cladding: architectural concrete panels on an alum…
C$178,025.45
Installation of prefabricated reinforced concrete slabs…
C$135,977.20
Installation of metal fences on reinforced concrete pos…
C$41,019.36
Device for: vibration tablet compaction
C$22,728.73
Installation of wooden supports in marshy ground: corne…
C$16,802.09
What-If Scenarios
iExplore how changes in material, labor, or equipment costs affect the total project budget
Optimistic (-10%)
C$451,089.19
↓ C$50,121.02 savings
Labor -10% · Materials -10% · Equipment -10%
Base Estimate
C$501,210.21
Deterministic
Labor ×1.00 · Materials ×1.00 · Equipment ×1.00
Pessimistic (+15%)
C$576,391.74
↑ C$75,181.53 increase
Labor +15% · Materials +15% · Equipment +15%
Custom Scenario: Adjust cost components
Labor0%
Materials0%
Equipment0%
Custom Scenario Total Cost
C$501,210.21
Clicking Apply will update PPP coefficients and recalculate all line items
Project Schedule
≈9 monthsiProject timeline with critical path method (CPM), Gantt chart, and resource allocation
Construction PhasesAI
Site PreparationSite clearing, temporary facilities setup, utilities connection65d
MEP Finish WorkElectrical fixtures, plumbing fixtures, HVAC units and controls40d
Interior DoorsInterior door installation, hardware, access control systems8d
Flooring InstallationCarpet, tile, hardwood, and other finish flooring systems8d
Painting and Final FinishesInterior painting, final wall finishes, trim work8d
Final Systems and TestingSystem commissioning, testing, safety systems, elevators8d
Landscaping and Site WorkExterior landscaping, parking areas, site cleanup8d
Final Inspection and HandoverFinal inspections, punch list completion, project handover8d
9
months
274
days
19
phases
15
Critical Path
13
Peak workers
4,464
Labor Hours
Site PreparationEarthworkFoundation WorkStructural FrameworkRoofing SystemExternal EnvelopeWindows and External DoorsMEP Rough-inInternal Walls FramingInsulationDrywall and PlasteringCeiling SystemsMEP Finish WorkInterior DoorsFlooring InstallationPainting and Final FinishesFinal Systems and TestingLandscaping and Site WorkFinal Inspection and HandoverCumulative Cost
Labor Hours by Phase
Structural Framework
2,276 hours
Site Preparation
1,033 hours
MEP Finish Work
633 hours
Foundation Work
447 hours
Flooring Installatio
63 hours
Earthwork
50 hours
External Envelope
50 hours
Windows and External
50 hours
MEP Rough-in
50 hours
Internal Walls Frami
50 hours
Insulation
50 hours
Drywall and Plasteri
50 hours
Ceiling Systems
50 hours
Interior Doors
50 hours
Painting and Final F
50 hours
Final Systems and Te
50 hours
Landscaping and Site
50 hours
Final Inspection and
50 hours
Roofing System
13 hours
Monthly Cash Flow
9 monthsiMonthly cost distribution and cumulative S-curve showing how project spending builds over time
5%
M1
9%
M2
12%
M3
25%
M4
86%
M5
95%
M6
96%
M7
99%
M8
100%
M9
Month
days
Monthly Cost
%
Cumulative
%
M1
1–30
C$22,947.88
4.6%
C$22,947.88
5%
M2
31–60
C$22,947.88
4.6%
C$45,895.75
9%
M3
61–90
C$14,034.47
2.8%
C$59,930.22
12%
M4
91–120
C$66,159.81
13.2%
C$126,090.03
25%
M5
121–150
C$306,872.19
61.2%
C$432,962.22
86%
M6
151–180
C$42,670.53
8.5%
C$475,632.75
95%
M7
181–210
C$4,099.27
0.8%
C$479,732.02
96%
M8
211–240
C$15,372.28
3.1%
C$495,104.30
99%
M9
241–270
C$6,105.91
1.2%
C$501,210.21
100%
Daily Cash Flow
36 weeks
0%
D1
4%
D25
7%
D49
10%
D73
13%
D97
27%
D121
76%
D145
95%
D169
95%
D193
96%
D217
99%
D241
100%
D249
Week
days
Weekly Cost
%
Cumulative
%
W1
D1–D7
C$5,354.50
1.1%
C$5,354.50
1%
W2
D8–D14
C$5,354.50
1.1%
C$10,709.01
2%
W3
D15–D21
C$5,354.50
1.1%
C$16,063.51
3%
W4
D22–D28
C$5,354.50
1.1%
C$21,418.02
4%
W5
D29–D35
C$5,354.50
1.1%
C$26,772.52
5%
W6
D36–D42
C$5,354.50
1.1%
C$32,127.03
6%
W7
D43–D49
C$5,354.50
1.1%
C$37,481.53
7%
W8
D50–D56
C$5,354.50
1.1%
C$42,836.04
9%
W9
D57–D63
C$5,354.50
1.1%
C$48,190.54
10%
W10
D64–D70
C$1,529.86
0.3%
C$49,720.40
10%
W11
D71–D77
C$2,402.31
0.5%
C$52,122.71
10%
W12
D78–D84
C$4,204.04
0.8%
C$56,326.75
11%
W13
D85–D91
C$4,204.04
0.8%
C$60,530.80
12%
W14
D92–D98
C$4,204.04
0.8%
C$64,734.84
13%
W15
D99–D105
C$4,204.04
0.8%
C$68,938.88
14%
W16
D106–D112
C$4,204.04
0.8%
C$73,142.93
15%
W17
D113–D119
C$42,718.03
8.5%
C$115,860.95
23%
W18
D120–D126
C$71,603.51
14.3%
C$187,464.46
37%
W19
D127–D133
C$71,603.51
14.3%
C$259,067.98
52%
W20
D134–D140
C$71,603.51
14.3%
C$330,671.49
66%
W21
D141–D147
C$71,603.51
14.3%
C$402,274.00
80%
W22
D148–D154
C$71,603.51
14.3%
C$473,878.51
95%
W23
D155–D161
C$1,534.96
0.3%
C$475,413.47
95%
W24
D162–D168
C$219.28
0.0%
C$475,632.75
95%
W25
D169–D175
C$0.00
0.0%
C$475,632.75
95%
W26
D176–D182
C$0.00
0.0%
C$475,632.75
95%
W27
D183–D189
C$0.00
0.0%
C$475,632.75
95%
W28
D190–D196
C$0.00
0.0%
C$475,632.75
95%
W29
D197–D203
C$512.41
0.1%
C$476,145.16
95%
W30
D204–D210
C$3,586.86
0.7%
C$479,732.02
96%
W31
D211–D217
C$3,586.86
0.7%
C$483,318.89
96%
W32
D218–D224
C$3,586.86
0.7%
C$486,905.75
97%
W33
D225–D231
C$3,586.86
0.7%
C$490,492.62
98%
W34
D232–D238
C$3,586.86
0.7%
C$494,079.48
99%
W35
D239–D245
C$3,955.05
0.8%
C$498,034.53
99%
W36
D246–D250
C$3,175.68
0.6%
C$501,210.21
100%
Line Items
36 itemsiDetailed work items grouped by category with quantities, unit prices, and resource breakdown
▼Site & Earthworks4 itemsC$29,847.91
#
Code
Description
Qty
Unit
Unit Price
Total
1
KAME_KARI_KAVOLI_KAPU
Snow removal from construction sites and roads: bulldozers with movements at a distance of every subsequent 10 m
700.0
700 m²(Site & Earthworks)
m3
C$0.04
C$31.27
C$24.72 +15% C$3.71+10% C$2.84
Labor Materials Equipment
Type
Resource
Qty
Unit
Unit Price
Cost
Bulldozers, power 79 kW (108 hp)
0.48
Machine hours
C$37.94
C$18.06
Personnel: 1 person-hour/machine-hour
0.48
Machine hours
C$13.99
C$6.66
2
KAVO_KAME_KANEDX_KARIm
Assembled busbar - two strips in phase, copper or aluminum with a cross-section: over 250 to 500 mm2
140.0
140 m³(Site & Earthworks)
m
C$28.14
C$4,984.13
C$3,940.03 +15% C$591.00+10% C$453.10
Labor Materials Equipment
Type
Resource
Qty
Unit
Unit Price
Cost
Worker Category 1
134.12
hrs
C$25.20
C$3,379.21
Gaseous argon, grade I
1.43
m3
C$11.91
C$17.00
Bolts with nuts and washers for construction
18.62
kg
C$8.06
C$150.17
MA-0115 oil paint, mummy, iron minium
4.10
kg
C$4.83
C$19.80
Mobile cranes, lifting capacity 16 t
0.88
Machine hours
C$62.03
C$54.71
Personnel: 1 person-hour/machine-hour
0.88
Machine hours
C$17.95
C$15.84
Flatbed trucks, load capacity up to 5 tons
0.88
Machine hours
C$24.09
C$21.25
Personnel: 1 person-hour/machine-hour
0.88
Machine hours
C$13.36
C$11.79
Welding machines for manual arc welding, welding current up to 350 A
5.12
Machine hours
C$1.34
C$6.86
Drilling machines
3.18
Machine hours
C$1.19
C$3.79
Universal hydraulic pipe benders
17.64
Machine hours
C$1.35
C$23.88
Personnel: 1 person-hour/machine-hour
17.64
Machine hours
C$13.36
C$235.72
3
MEME_KAME_KAPUPU_KARI
Cutting joints in concrete: with joint filling using sealant when installing polymer self-leveling floors
200.0
200 m³(Site & Earthworks)
m
C$8.32
C$2,103.78
C$1,663.07 +15% C$249.46+10% C$191.25
Labor Materials Equipment
Type
Resource
Qty
Unit
Unit Price
Cost
Worker Category 1
19.42
hrs
C$21.86
C$424.46
Drying paste-like sealant-adhesive based on organic solvents for sealing radio equipment, fastening radio components, harnesses, wires, operating temperature range from -70 to +85 °C
6.70
kg
C$83.84
C$561.76
Concrete paving machines on rail forms Joint cutters for freshly laid cement concrete
5.60
Machine hours
C$102.74
C$575.34
Personnel: 1 person-hour/machine-hour
5.60
Machine hours
C$17.99
C$100.76
Flatbed trucks, load capacity up to 5 tons
0.02
Machine hours
C$24.14
C$0.48
Personnel: 1 person-hour/machine-hour
0.02
Machine hours
C$13.39
C$0.27
4
TOPU_KARI_KAKAVO_SATOm
Device for: vibration tablet compaction
600.0
600 m²(Site & Earthworks)
pcs
C$29.95
C$22,728.73
C$17,967.38 +15% C$2,695.11+10% C$2,066.25
Labor Materials Equipment
Type
Resource
Qty
Unit
Unit Price
Cost
Worker Category 1
618.00
hrs
C$27.76
C$17,156.72
Mobile cranes, lifting capacity 16 t
6.00
Machine hours
C$65.89
C$395.37
Personnel: 1 person-hour/machine-hour
6.00
Machine hours
C$18.94
C$113.65
Trucks, load capacity up to 8 tons
6.00
Machine hours
C$36.18
C$217.05
Personnel: 1 person-hour/machine-hour
6.00
Machine hours
C$14.10
C$84.59
▼Foundations4 itemsC$37,008.99
#
Code
Description
Qty
Unit
Unit Price
Total
5
KALI_KASA_KAKAPU_KAVO
Installation of columns with steel cores on foundations and lower columns with a mass of: over 3 to 4 tons
20.0
20 m³(Foundations)
pcs
C$332.89
C$8,422.17
C$6,657.84 +15% C$998.68+10% C$765.65
Labor Materials Equipment
Type
Resource
Qty
Unit
Unit Price
Cost
Worker Category 1
177.40
hrs
C$25.33
C$4,493.08
Welding electrodes for welding low-alloy and carbon steels ANO-6, E42, diameter 6 mm
0.10
t
C$5,426.02
C$542.60
Edged softwood boards, natural moisture content, length RI-NE.SA m, width 100-250 mm, thickness 44-50 mm, grade II
0.17
m3
C$555.73
C$96.70
Tower cranes, lifting capacity 8 t
26.40
Machine hours
C$38.58
C$1,018.55
Personnel: 1 person-hour/machine-hour
26.40
Machine hours
C$17.79
C$469.63
Flatbed trucks, load capacity up to 5 tons
0.47
Machine hours
C$23.87
C$11.17
Personnel: 1 person-hour/machine-hour
0.47
Machine hours
C$13.24
C$6.20
Welding machines for manual arc welding, welding current up to 350 A
15.00
Machine hours
C$1.33
C$19.91
6
TOPU_KARI_KARINE_KAPU
Installation of wooden supports in marshy ground: corner with two supports and beams
12.0
12 m³(Foundations)
pcs
C$1,106.86
C$16,802.09
C$13,282.28 +15% C$1,992.34+10% C$1,527.46
Labor Materials Equipment
Type
Resource
Qty
Unit
Unit Price
Cost
Worker Category 1
231.60
hrs
C$39.25
C$9,089.31
Bolts with nuts and washers for construction
134.40
kg
C$4.98
C$668.68
Colored cotton rags
0.12
kg
C$2.17
C$0.26
Dead ends
0.12
100 pcs
C$8.73
C$1.05
U-1 slope fastening unit
48.00
pcs
C$49.30
C$2,366.36
Bulldozers, power 59 kW (80 hp)
10.80
Machine hours
C$80.10
C$865.09
Personnel: 1 person-hour/machine-hour
10.80
Machine hours
C$26.30
C$284.02
Manual and lever winches with a pulling force of up to DX.VOME kN (1 t)
57.84
Machine hours
C$0.13
C$7.51
7
RIDX_KARI_KAPUNE_KASA
Reinforcement of monolithic reinforced concrete columns
2.5
2500 kg(Foundations)
t
C$3,327.26
C$10,522.46
C$8,318.16 +15% C$1,247.72+10% C$956.59
Labor Materials Equipment
Type
Resource
Qty
Unit
Unit Price
Cost
Worker Category 1
89.17
hrs
C$26.32
C$2,347.32
Welding electrodes for welding low-alloy and carbon steels UONI 13/45, E42A, diameter 4-5 mm
1.50
kg
C$372.29
C$558.17
Low-carbon steel knitting wire
0.03
t
C$213,536.72
C$5,338.61
Mobile cranes, lifting capacity 16 t
0.35
Machine hours
C$66.70
C$23.35
Personnel: 1 person-hour/machine-hour
0.35
Machine hours
C$19.20
C$6.71
Flatbed trucks, load capacity up to 10 tons
0.47
Machine hours
C$37.19
C$17.67
Personnel: 1 person-hour/machine-hour
0.47
Machine hours
C$14.29
C$6.79
Welding machines for manual arc welding, welding current up to 350 A
0.07
Machine hours
C$1.44
C$0.10
Crank-type guillotine sheet metal shears
1.95
Machine hours
C$8.77
C$17.09
Rebar bending machines
1.93
Machine hours
C$1.22
C$2.35
8
MEME_KAME_KAPUPU_KARI
Cutting joints in concrete: with joint filling using sealant when installing polymer self-leveling floors
120.0
120 m(Foundations)
m
C$8.32
C$1,262.27
C$997.84 +15% C$149.68+10% C$114.75
Labor Materials Equipment
Type
Resource
Qty
Unit
Unit Price
Cost
Worker Category 1
11.65
hrs
C$21.86
C$254.67
Drying paste-like sealant-adhesive based on organic solvents for sealing radio equipment, fastening radio components, harnesses, wires, operating temperature range from -70 to +85 °C
4.02
kg
C$83.85
C$337.06
Concrete paving machines on rail forms Joint cutters for freshly laid cement concrete
3.36
Machine hours
C$102.74
C$345.20
Personnel: 1 person-hour/machine-hour
3.36
Machine hours
C$17.99
C$60.46
Flatbed trucks, load capacity up to 5 tons
0.01
Machine hours
C$24.14
C$0.29
Personnel: 1 person-hour/machine-hour
0.01
Machine hours
C$13.39
C$0.16
▼Steel Structure3 itemsC$5,607.14
#
Code
Description
Qty
Unit
Unit Price
Total
9
KAVO_KARI_MESARI_KAMEm
Corner steel shelf bracket
1.0
1 t(Steel Structure)
t
C$2,246.77
C$2,842.17
C$2,246.77 +15% C$337.02+10% C$258.38
Labor Materials Equipment
Type
Resource
Qty
Unit
Unit Price
Cost
Worker Category 1
80.80
hrs
C$26.26
C$2,121.60
Welding electrodes for welding low-alloy and carbon steels UONI 13/45, E42A, diameter 4-5 mm
2.99
kg
C$6.14
C$18.34
Portland cement without additives for general construction CEM 0 32.5N
0.01
t
C$339.73
C$3.40
BT-123 bitumen varnish
0.01
t
C$4,695.75
C$46.96
Mobile cranes, lifting capacity 16 t
0.20
Machine hours
C$66.16
C$13.23
Personnel: 1 person-hour/machine-hour
0.20
Machine hours
C$19.15
C$3.83
Flatbed trucks, load capacity up to 5 tons
0.20
Machine hours
C$25.69
C$5.14
Personnel: 1 person-hour/machine-hour
0.20
Machine hours
C$14.25
C$2.85
Welding machines for manual arc welding, welding current up to 350 A
22.00
Machine hours
C$1.43
C$31.42
10
KADX_KASA_KAKATO_KARI
Bolt placement: high-strength
1.0
1 set(Steel Structure)
pcs
C$6.16
C$7.79
C$6.16 +15% C$0.92+10% C$0.71
Labor Materials Equipment
Type
Resource
Qty
Unit
Unit Price
Cost
Worker Category 1
0.16
hrs
C$34.65
C$5.58
Technical gaseous oxygen
0.06
m3
C$8.48
C$0.51
Dry moisture-resistant gypsum-based putty mixtures with polymer and hydrophobic additives, aggregate size no more than KA.RI mm, flexural strength not less than ME.SA MPa
0.01
kg
C$2.83
C$0.04
Flatbed trucks, load capacity up to 5 tons
0.00
Machine hours
C$27.51
C$0.01
Personnel: 1 person-hour/machine-hour
0.00
Machine hours
C$18.38
C$0.01
Gas welding and cutting equipment
0.06
Machine hours
C$0.24
C$0.01
11
TODX_KAME_KAMESA_KASA
Installation of anchor rods in a closed water area when supplying structural elements: from the shore using a crawler cr
3.0
3 days(Steel Structure)
t
C$726.53
C$2,757.18
C$2,179.59 +15% C$326.94+10% C$250.65
Labor Materials Equipment
Type
Resource
Qty
Unit
Unit Price
Cost
Worker Category 1
56.10
hrs
C$24.43
C$1,370.54
Bitumen petroleum construction insulation BNI-IV-3, BNI-IV, BNI-V
0.06
t
C$1,139.16
C$68.35
Grease, solid, fat-based, type Z
3.00
kg
C$4.63
C$13.90
Acetylene gas, technical grade
0.12
m3
C$23.62
C$2.84
Technical gaseous oxygen
0.54
m3
C$6.31
C$3.41
Welding electrodes for welding low-alloy and carbon steels UONI 13/45, E42A, diameter 4-5 mm
3.00
kg
C$5.84
C$17.53
Burlap fabric, width 950 mm, surface density 190 g/m2
3.54
10 m
C$37.74
C$133.62
Hot-rolled smooth reinforcing steel, class A-I, diameter 6-22 mm
0.03
t
C$1,968.83
C$59.07
Coal tar for road construction
0.06
t
C$262.09
C$15.72
Crawler cranes, lifting capacity 25 t
4.02
Machine hours
C$92.09
C$370.20
Personnel: 1 person-hour/machine-hour
4.02
Machine hours
C$18.23
C$73.28
Pneumatic wheeled cranes, lifting capacity 30 t
0.21
Machine hours
C$79.61
C$16.72
Personnel: 1 person-hour/machine-hour
0.21
Machine hours
C$19.45
C$4.08
Mobile electric bitumen boilers with centrifugal mixer, loading capacity 400 l
1.35
Machine hours
C$5.45
C$7.36
Flatbed trucks, load capacity up to 5 tons
0.06
Machine hours
C$24.46
C$1.47
Personnel: 1 person-hour/machine-hour
0.06
Machine hours
C$13.57
C$0.82
Tractor units, load on the fifth wheel coupling up to 15 t
0.24
Machine hours
C$43.92
C$10.54
Personnel: 1 person-hour/machine-hour
0.24
Machine hours
C$15.60
C$3.74
General purpose semi-trailers, load capacity up to 15 t
0.24
Machine hours
C$6.57
C$1.57
Welding units with internal combustion engines for manual arc welding, welding current up to 400 A, number of stations 1
1.11
Machine hours
C$4.24
C$4.71
Gas welding and cutting equipment
0.60
Machine hours
C$0.21
C$0.12
▼Envelope5 itemsC$200,934.26
#
Code
Description
Qty
Unit
Unit Price
Total
12
RIDX_KARI_KALIRI_KARI
Wall cladding: architectural concrete panels on an aluminum alloy suspension system
350.0
350 m²(Envelope)
m2
C$402.09
C$178,025.45
C$140,731.58 +15% C$21,109.74+10% C$16,184.13
Labor Materials Equipment
Type
Resource
Qty
Unit
Unit Price
Cost
2nd grade worker
298.51
hrs
C$23.80
C$7,104.08
Grade 3 worker
46.41
hrs
C$25.99
C$1,206.03
Grade 4 worker
1,013.14
hrs
C$29.27
C$29,653.63
Electricity
132.90
kWh
C$2.45
C$326.04
Stainless steel collet anchors with conical spacer sleeve for concealed fastening of cladding panels on ventilated curtain walls, complete with hexagon head bolt and cylindrical collar, M6x10, installation depth 7 mm
14.98
100 pcs
C$1,970.64
C$29,520.20
Galvanized steel friction wedge anchors for crack-free concrete, external thread M10, length 98 mm
124.81
10 pcs
C$409.29
C$51,083.05
Flat cutting disc, dimensions 125x2.5x22 mm
37.94
pcs
C$9.30
C$352.71
Drill bit with diamond tip for drilling holes for collet anchors, drilling depth up to 15 mm, diameter LI.RI mm with reaming up to 9 mm
7.42
pcs
C$2,356.82
C$17,487.59
Drill bit with carbide tip, SDS-plus shank for hammer drilling holes in hard materials, total length 160 mm, diameter 10 mm
1.26
pcs
C$28.66
C$36.12
Spiral drill bits with cylindrical shank made of high-speed steel P6M5, accuracy class A1, length 86 mm, diameter 5 mm
0.39
100 pcs
C$2,647.32
C$1,019.24
Two-component adhesive injection compound based on vinyl ester resin for heavy-duty anchor fastenings in concrete, operating temperature from -40 °C to +40 °C
1.96
l
C$626.32
C$1,227.56
Mobile cranes, lifting capacity 16 t
12.95
Machine hours
C$72.74
C$942.02
Personnel: 1 person-hour/machine-hour
12.95
Machine hours
C$20.86
C$270.11
General-purpose electric hoists, load capacity KA.SA t
117.08
Machine hours
C$0.33
C$38.39
Flatbed trucks, load capacity up to 10 tons
6.86
Machine hours
C$40.56
C$278.22
Personnel: 1 person-hour/machine-hour
6.86
Machine hours
C$15.52
C$106.49
Mobile piston compressors with electric motor, pressure up to KA.NE MPa (6 atm), capacity up to KA.VOTO m3/min
31.15
Machine hours
C$0.76
C$23.65
Machines for drilling blind holes for anchors, power ME.PU kW
31.15
Machine hours
C$1.81
C$56.45
13
MERI_KAME_KAKAPU_KASA
Installation of flashings for roofs made of weldable materials to walls and parapets with a height of: more than 600 mm
25.0
25 m(Envelope)
m
C$55.47
C$1,754.24
C$1,386.75 +15% C$208.01+10% C$159.48
Labor Materials Equipment
Type
Resource
Qty
Unit
Unit Price
Cost
Worker Category 1
13.05
hrs
C$30.94
C$403.84
Propane-butane technical mixture
6.13
kg
C$11.82
C$72.44
Cartridges for construction and installation gun, red tip, length 10-18 mm
0.05
1000 pcs
C$867.85
C$41.22
Ready-mixed masonry mortar, cement, M100
0.13
m3
C$847.46
C$108.04
Galvanized sheet steel, thickness KA.LI mm
0.05
t
C$12,849.28
C$642.46
Hot-rolled steel strip, steel grades St3sp, St3ps, dimensions 50x5 mm
0.00
t
C$10,189.25
C$25.48
Two-component thiokol mastic for construction purposes, cold curing
1.68
kg
C$46.26
C$77.50
Tower cranes, lifting capacity 8 t
0.14
Machine hours
C$50.66
C$6.84
Personnel: 1 person-hour/machine-hour
0.14
Machine hours
C$23.09
C$3.12
Mobile cranes, lifting capacity 16 t
0.03
Machine hours
C$80.70
C$2.62
Personnel: 1 person-hour/machine-hour
0.03
Machine hours
C$23.09
C$0.75
Flatbed trucks, load capacity up to 5 tons
0.05
Machine hours
C$31.34
C$1.57
Personnel: 1 person-hour/machine-hour
0.05
Machine hours
C$17.18
C$0.86
14
MEKA_KAME_KANEKA_KANE
Finishing protruding wall corners with trims: softwoods on brick and concrete (unpainted)
60.0
60 m(Envelope)
m
C$52.58
C$3,991.11
C$3,155.04 +15% C$473.25+10% C$362.83
Labor Materials Equipment
Type
Resource
Qty
Unit
Unit Price
Cost
Average work load RI.DX
55.80
hrs
C$23.76
C$1,325.89
Edged softwood boards, natural moisture content, length RI-NE.SA m, width 100-250 mm, thickness 44-50 mm, grade III
0.02
m3
C$101,446.40
C$1,826.01
Flatbed trucks, load capacity up to 5 tons
0.08
Machine hours
C$25.84
C$2.02
Personnel: 1 person-hour/machine-hour
0.08
Machine hours
C$14.32
C$1.12
15
KAME_KARI_KAPUVO_KAME
Reinforcement of uphill and drainage ditches, culverts: gutters
50.0
50 m(Envelope)
m
C$262.09
C$16,576.93
C$13,104.29 +15% C$1,965.64+10% C$1,506.99
Labor Materials Equipment
Type
Resource
Qty
Unit
Unit Price
Cost
Average workload TO.KA
109.50
hrs
C$20.36
C$2,229.66
Crawler cranes, lifting capacity 25 t
23.50
Machine hours
C$96.77
C$2,274.10
Personnel: 1 person-hour/machine-hour
23.50
Machine hours
C$16.34
C$384.07
Reinforcement of uphill and drainage ditches, culverts: gutters
50.00
m
C$164.33
C$8,216.46
16
SAVO_KAME_KATOPU_KARI
Installation of drainpipes: from removable mounting towers
24.0
24 m(Envelope)
m
C$19.32
C$586.53
C$463.66 +15% C$69.55+10% C$53.32
Labor Materials Equipment
Type
Resource
Qty
Unit
Unit Price
Cost
Worker Category 1
10.67
hrs
C$24.50
C$261.32
Simple construction forgings (staples, fasteners, clamps), weight up to ME.NE kg
22.80
kg
C$6.73
C$153.37
Single-mast hoists, load capacity up to 500 kg, lifting height 45 m
3.55
Machine hours
C$2.16
C$7.68
Personnel: 1 person-hour/machine-hour
3.55
Machine hours
C$11.55
C$41.02
Flatbed trucks, load capacity up to 5 tons
0.01
Machine hours
C$23.44
C$0.17
Personnel: 1 person-hour/machine-hour
0.01
Machine hours
C$12.99
C$0.09
▼Openings4 itemsC$5,294.50
#
Code
Description
Qty
Unit
Unit Price
Total
17
MEKA_MEKA_KAKAVO_KARIm
Installation of automatic sliding doors: double-leaf, with a leaf weight of up to 160 kg
2.0
2 pcs(Openings)
set
C$302.09
C$764.30
C$604.19 +15% C$90.63+10% C$69.48
Labor Materials Equipment
Type
Resource
Qty
Unit
Unit Price
Cost
Worker Category 1
23.94
hrs
C$25.03
C$599.14
Electricity
1.38
kWh
C$0.30
C$0.41
Flatbed trucks, load capacity up to 6 tons, with crane-manipulator, load capacity 4 tons
0.08
Machine hours
C$43.77
C$3.50
Personnel: 1 person-hour/machine-hour
0.08
Machine hours
C$14.23
C$1.14
18
KADX_KAPU_KAMETO_KANE
Installation of fire doors on anchors: double-hung
2.0
2 pcs(Openings)
pcs
C$1,104.10
C$2,793.36
C$2,208.20 +15% C$331.23+10% C$253.94
Labor Materials Equipment
Type
Resource
Qty
Unit
Unit Price
Cost
Worker Category 1
18.76
hrs
C$25.32
C$475.07
Electricity
0.73
kWh
C$8.15
C$5.87
Steel frame mounting dowels, diameter 10 mm, length 130 (132) mm
1.60
10 pcs
C$132.92
C$212.57
Drill bit with carbide tip, SDS-plus shank for hammer drilling holes in hard materials, total length 260 mm, diameter 10 mm
1.60
pcs
C$123.05
C$197.00
Ready-mixed masonry mortar, cement, M150
0.00
m3
C$5,942.66
C$11.99
Universal acrylic sealant for filling joints and cracks, sealing joints
0.70
l
C$432.62
C$303.67
Fire-resistant polyurethane foam sealant (assembly foam) for areas with increased fire safety requirements, volume 880 ml
1.52
pcs
C$653.44
C$993.17
Construction freight and passenger lifts, lifting capacity up to KA.VO t, lifting height up to 80 m
0.13
Machine hours
C$17.63
C$2.29
Personnel: 1 person-hour/machine-hour
0.13
Machine hours
C$14.57
C$1.89
Flatbed trucks, load capacity up to 5 tons
0.11
Machine hours
C$26.46
C$3.02
Personnel: 1 person-hour/machine-hour
0.11
Machine hours
C$14.57
C$1.66
19
NENE_KAME_KAMELI_RIVO
Dismantling of pipelines in accessible channels through inspection windows with pipe diameters: up to 1000 mm
10.0
10 m²(Openings)
m
C$81.07
C$1,025.50
C$810.67 +15% C$121.60+10% C$93.23
Labor Materials Equipment
Type
Resource
Qty
Unit
Unit Price
Cost
Average work load RI.DX
29.60
hrs
C$22.98
C$680.33
Technical gaseous oxygen
3.75
m3
C$6.44
C$24.14
Propane-butane technical mixture
0.91
kg
C$2.82
C$2.57
Mobile cranes, lifting capacity 16 t
1.23
Machine hours
C$64.29
C$79.01
Personnel: 1 person-hour/machine-hour
1.23
Machine hours
C$18.61
C$22.87
Flatbed trucks, load capacity up to 5 tons
0.04
Machine hours
C$24.97
C$1.00
Personnel: 1 person-hour/machine-hour
0.04
Machine hours
C$13.85
C$0.55
Gas welding and cutting equipment
0.91
Machine hours
C$0.21
C$0.20
20
RIPU_KARI_MEMEKA_KAMEm
Device for unloading radiator sections from a suspended conveyor
1.0
1 pcs(Openings)
pcs
C$562.32
C$711.34
C$562.32 +15% C$84.35+10% C$64.67
Labor Materials Equipment
Type
Resource
Qty
Unit
Unit Price
Cost
Worker Category 1
19.60
hrs
C$26.01
C$509.84
Electricity
24.00
kWh
C$0.29
C$7.00
Mobile cranes, lifting capacity 16 t
0.37
Machine hours
C$64.77
C$23.96
Personnel: 1 person-hour/machine-hour
0.37
Machine hours
C$18.75
C$6.93
Electric winches with a pulling force of up to SA.LIDX kN (KA.SADX t)
0.30
Machine hours
C$0.40
C$0.12
Flatbed trucks, load capacity up to 5 tons
0.37
Machine hours
C$25.15
C$9.31
Personnel: 1 person-hour/machine-hour
0.37
Machine hours
C$13.95
C$5.16
▼Office Area (50 m²)5 itemsC$21,919.52
#
Code
Description
Qty
Unit
Unit Price
Total
21
MEKA_KASA_KAKAPU_KAME
Installation of partitions made of plasterboard sheets (drywall) with a double metal frame and two-layer cladding on bot
40.0
40 m²(Office Area (50 m²))
m2
C$106.02
C$5,364.67
C$4,240.85 +15% C$636.13+10% C$487.70
Labor Materials Equipment
Type
Resource
Qty
Unit
Unit Price
Cost
Worker Category 1
72.80
hrs
C$34.89
C$2,539.95
Water
0.05
m3
C$2.57
C$0.13
Electricity
1.58
kWh
C$0.42
C$0.66
Elastic self-adhesive tapes for guide profiles 50x30000 mm
106.80
m
C$0.46
C$49.61
Perforated paper reinforcement tapes for increasing the crack resistance of joints, width 52 mm
60.80
m
C$0.15
C$9.41
Paper tapes for creating artificial cracks between frame structures and adjacent surfaces, with an adhesive layer on one side and an anti-adhesive coating on the other, white, width 65 mm
0.71
100 m
C$184.51
C$130.63
Plastic dowels with screws, diameter 6 mm, length 35 mm, screw diameter TO.SA mm, screw length 50 mm
1.35
100 pcs
C$4.29
C$5.81
Self-tapping steel screws, oxidized, with countersunk head and cross-shaped slot, pointed, diameter TO.SA mm, length 25 mm
5.41
100 pcs
C$1.68
C$9.10
Self-tapping steel screws, oxidized, with countersunk head and cross-shaped slot, pointed, diameter TO.SA mm, length 35 mm
14.13
100 pcs
C$2.19
C$30.95
Galvanized steel guide profile for installing gypsum partitions and suspended ceilings, dimensions 50x40 mm, steel thickness KA.NE mm
60.40
m
C$3.85
C$232.48
Galvanized steel rack profile, dimensions 50x50 mm, thickness KA.NE mm
162.80
m
C$6.08
C$990.36
Deep-penetrating, quick-drying, vapor-permeable strengthening primer
8.00
kg
C$6.57
C$52.56
Dry putty mixes based on high-strength gypsum with polymer additives, aggregate size no more than KA.MESA mm, flexural strength RI.LI MPa
8.40
kg
C$5.77
C$48.50
Universal dry putty mixtures based on gypsum with polymer additives, aggregate size not exceeding KA.RI mm, flexural strength not less than ME.KA MPa
59.60
kg
C$1.50
C$89.66
Mobile cranes, lifting capacity 16 t
0.36
Machine hours
C$91.46
C$33.29
Personnel: 1 person-hour/machine-hour
0.36
Machine hours
C$26.34
C$9.59
Flatbed trucks, load capacity up to 5 tons
0.15
Machine hours
C$35.52
C$5.26
Personnel: 1 person-hour/machine-hour
0.15
Machine hours
C$19.60
C$2.90
Electric shears
0.08
Machine hours
C$0.20
C$0.01
22
MEKA_KALI_KAMERI_KAME
Installation of suspended ceilings made of reinforced cement-mineral slabs, internal: on a wooden frame
50.0
50 m²(Office Area (50 m²))
m2
C$93.18
C$5,893.72
C$4,659.06 +15% C$698.86+10% C$535.79
Labor Materials Equipment
Type
Resource
Qty
Unit
Unit Price
Cost
Worker Category 1
55.00
hrs
C$28.35
C$1,559.01
Electricity
1.58
kWh
C$1.77
C$2.78
Alkali-resistant glass fiber reinforcement tape, width 100 mm, length 50000 mm
2.12
pcs
C$316.27
C$670.50
Polypropylene anchor dowel nails with flange, diameter 6 mm, length 40 mm
1.77
100 pcs
C$55.81
C$99.03
Self-tapping steel screws with anti-corrosion coating, countersunk head and cross-shaped slot, double-start thread, pointed tip, diameter PU.RI mm, length 25 mm
1.62
1000 pcs
C$379.54
C$616.73
Self-tapping steel screws, oxidized, with countersunk head and cross-shaped slot, pointed, diameter PU.RI mm, length 75 mm
3.19
100 pcs
C$22.30
C$71.26
Sanding paper
2.10
m2
C$73.91
C$155.24
Dry concrete mixes, non-shrinking, fast-setting, containing polymer and rigid steel fibers, for repairing concrete and reinforced concrete elements of bridge structures, airfield and road pavements subject to dynamic and impact loads, aggregate size 10 mm
36.00
kg
C$24.64
C$886.94
Galvanized steel straight hangers for attaching suspended ceilings to profiles, profile dimensions 60x27 mm, hanger length 300 mm, thickness KA.LI mm
1.75
100 pcs
C$320.37
C$560.64
Mobile cranes, lifting capacity 16 t
0.31
Machine hours
C$74.41
C$23.06
Personnel: 1 person-hour/machine-hour
0.31
Machine hours
C$21.40
C$6.63
Single-mast hoists, load capacity up to 500 kg, lifting height 45 m
0.12
Machine hours
C$2.67
C$0.34
Personnel: 1 person-hour/machine-hour
0.12
Machine hours
C$14.16
C$1.76
Flatbed trucks, load capacity up to 5 tons
0.12
Machine hours
C$28.90
C$3.32
Personnel: 1 person-hour/machine-hour
0.12
Machine hours
C$15.93
C$1.83
23
SALI_KAME_KAMEME_KASA
Installation of bases for floor covering: from chipboard with an area of up to 20 m2
50.0
50 m²(Office Area (50 m²))
m2
C$27.12
C$1,715.04
C$1,355.77 +15% C$203.36+10% C$155.91
Labor Materials Equipment
Type
Resource
Qty
Unit
Unit Price
Cost
Worker Category 1
23.03
hrs
C$23.24
C$535.33
Plywood boards type P1, standard unpolished, formaldehyde emission class E1, without facing, grade II, thickness 15-17 mm
0.51
100 m2
C$514.04
C$262.16
KN-2 rubber adhesive mastic
66.50
kg
C$8.36
C$555.93
Single-mast hoists, load capacity up to 500 kg, lifting height 45 m
0.05
Machine hours
C$2.37
C$0.12
Personnel: 1 person-hour/machine-hour
0.05
Machine hours
C$12.66
C$0.63
Flatbed trucks, load capacity up to 5 tons
0.04
Machine hours
C$25.72
C$1.03
Personnel: 1 person-hour/machine-hour
0.04
Machine hours
C$14.24
C$0.57
24
NEDX_KAME_KARIPU_KANE
Pontoon painting
90.0
90 m²(Office Area (50 m²))
m2
C$77.78
C$8,854.91
C$6,999.93 +15% C$1,049.99+10% C$804.99
Labor Materials Equipment
Type
Resource
Qty
Unit
Unit Price
Cost
Worker Category 1
35.10
hrs
C$22.09
C$775.25
Technical orthophosphoric acid
5.40
kg
C$3.02
C$16.31
Mobile screw compressors with electric motor, pressure up to KA.NE MPa (6 atm), capacity up to TO.SA m3/min
23.40
Machine hours
C$4.26
C$99.76
Tugs, power 221 kW (300 hp)
6.30
Machine hours
C$81.27
C$511.97
Personnel: 3 man-hours/machine-hours
6.30
Machine hours
C$37.09
C$233.68
Non-self-propelled floating cranes, 5 t
26.10
Machine hours
C$139.69
C$3,645.82
Personnel: 5 man-hours/machine-hours
26.10
Machine hours
C$61.82
C$1,613.50
Floating platforms, collapsible, load capacity TO.SA t
4.50
Machine hours
C$19.78
C$89.00
High-pressure painting units for painting structural surfaces, power 1 kW
17.10
Machine hours
C$0.20
C$3.44
Electric high-pressure devices for hydrocleaning surfaces, capacity 17 l/min, pressure 50 MPa
5.40
Machine hours
C$2.07
C$11.19
25
MEKA_KARI_KAPUNE_KATO
Assembly: toilet
1.0
1 set(Office Area (50 m²))
pcs
C$72.08
C$91.18
C$72.07 +15% C$10.81+10% C$8.29
Labor Materials Equipment
Type
Resource
Qty
Unit
Unit Price
Cost
Average work load RI.DX
2.72
hrs
C$26.34
C$71.65
Flatbed trucks, load capacity up to 5 tons
0.01
Machine hours
C$25.54
C$0.26
Personnel: 1 person-hour/machine-hour
0.01
Machine hours
C$15.87
C$0.16
▼MEP8 itemsC$23,012.42
#
Code
Description
Qty
Unit
Unit Price
Total
26
MEVO_KADX_KAKAME_KALIm
Distribution device with electric start, nominal passage diameter: 50 mm
1.0
1 set(MEP)
set
C$695.19
C$879.42
C$695.19 +15% C$104.28+10% C$79.95
Labor Materials Equipment
Type
Resource
Qty
Unit
Unit Price
Cost
Worker Category 1
25.00
hrs
C$27.17
C$679.13
Acetylene gas, technical grade
0.07
m3
C$24.70
C$1.73
Technical gaseous oxygen
0.11
m3
C$6.59
C$0.73
Uncoated welding wire SV-08G2S, diameter 2 mm
0.11
kg
C$4.53
C$0.50
Welding electrodes for welding low-alloy and carbon steels UONI 13/45, E42A, diameter 4-5 mm
0.08
kg
C$6.11
C$0.49
Mobile cranes, lifting capacity 16 t
0.09
Machine hours
C$65.89
C$5.93
Personnel: 1 person-hour/machine-hour
0.09
Machine hours
C$19.08
C$1.71
Electric winches with a pulling force of up to SA.LIDX kN (KA.SADX t)
0.17
Machine hours
C$0.41
C$0.07
Flatbed trucks, load capacity up to 5 tons
0.09
Machine hours
C$25.59
C$2.31
Personnel: 1 person-hour/machine-hour
0.09
Machine hours
C$14.20
C$1.28
Welding machines for manual arc welding, welding current up to 350 A
0.93
Machine hours
C$1.42
C$1.32
27
KAVO_KARI_TOVORI_KATOm
Linear LED lighting fixture, uncontrolled: from a car lift
20.0
20 pcs(MEP)
pcs
C$380.36
C$9,623.05
C$7,607.16 +15% C$1,141.07+10% C$874.82
Labor Materials Equipment
Type
Resource
Qty
Unit
Unit Price
Cost
Grade 3 worker
139.40
hrs
C$21.54
C$3,003.10
Grade 4 worker
100.40
hrs
C$24.26
C$2,436.12
Single-component silicone-based sealant, neutral
0.20
l
C$30.96
C$6.19
Auto hydraulic lifts, lifting height 12 m
37.20
Machine hours
C$19.64
C$730.75
Personnel: 1 person-hour/machine-hour
37.20
Machine hours
C$12.87
C$478.73
Flatbed trucks, load capacity up to 5 tons
26.40
Machine hours
C$23.20
C$612.52
Personnel: 1 person-hour/machine-hour
26.40
Machine hours
C$12.87
C$339.75
28
KAVO_KATO_SADXDX_MEPUm
Lighting panels installed on the wall: bolts on the structure, shield weight over 15 to 40 kg
8.0
8 pcs(MEP)
pcs
C$156.76
C$1,586.44
C$1,254.10 +15% C$188.12+10% C$144.22
Labor Materials Equipment
Type
Resource
Qty
Unit
Unit Price
Cost
Worker Category 1
37.28
hrs
C$28.03
C$1,045.09
Rubberized cotton insulating tape for electrical installation and repair work, black, width 20 mm, thickness KA.TOSA mm
38.64
m
C$0.25
C$9.83
Welding electrodes for welding low-alloy and carbon steels UONI 13/45, E42A, diameter 4-5 mm
0.40
kg
C$6.22
C$2.49
Bolts with nuts and washers for construction
3.28
kg
C$8.71
C$28.58
Polypropylene expansion anchors
0.32
100 pcs
C$2.23
C$0.71
MA-0115 oil paint, mummy, iron minium
0.80
kg
C$5.22
C$4.17
Flexible jumpers, type PGS-50
0.80
10 pcs
C$54.35
C$43.48
Insulating bushings, dimensions 65x50x18 mm
0.16
1000 pcs
C$210.50
C$33.68
U731M type clamps for main and branch wires and cables
0.32
100 pcs
C$104.33
C$33.39
Polyvinyl chloride electrical conduit, wall thickness KA.NE mm
2.00
kg
C$10.88
C$21.76
Mobile cranes, lifting capacity 16 t
0.24
Machine hours
C$67.03
C$16.09
Personnel: 1 person-hour/machine-hour
0.24
Machine hours
C$19.40
C$4.66
Flatbed trucks, load capacity up to 5 tons
0.24
Machine hours
C$26.03
C$6.25
Personnel: 1 person-hour/machine-hour
0.24
Machine hours
C$14.44
C$3.46
Welding machines for manual arc welding, welding current up to 350 A
0.32
Machine hours
C$1.45
C$0.46
29
KAVO_KATO_SADXME_KAVOm
Plug socket: non-recessed type with exposed wiring
20.0
20 pcs(MEP)
pcs
C$9.68
C$244.82
C$193.53 +15% C$29.03+10% C$22.26
Labor Materials Equipment
Type
Resource
Qty
Unit
Unit Price
Cost
Worker Category 1
6.91
hrs
C$27.75
C$191.82
Electricity
0.43
kWh
C$0.30
C$0.13
Rubberized cotton insulating tape for electrical installation and repair work, black, width 20 mm, thickness KA.TOSA mm
1.83
m
C$0.25
C$0.46
Polypropylene expansion anchors
0.20
100 pcs
C$2.20
C$0.45
Mobile cranes, lifting capacity 16 t
0.01
Machine hours
C$66.81
C$0.40
Personnel: 1 person-hour/machine-hour
0.01
Machine hours
C$19.20
C$0.11
Flatbed trucks, load capacity up to 5 tons
0.00
Machine hours
C$25.95
C$0.10
Personnel: 1 person-hour/machine-hour
0.00
Machine hours
C$14.29
C$0.06
30
MEKA_MEKA_KAMEKA_KARIm
Configuration of facility equipment for the hardware and software complex of the notification transmission system for jo
1.0
1 set(MEP)
set
C$89.08
C$112.69
C$89.08 +15% C$13.36+10% C$10.24
Labor Materials Equipment
Type
Resource
Qty
Unit
Unit Price
Cost
Grade 5 worker
0.46
hrs
C$31.19
C$14.34
Grade 6 worker
2.05
hrs
C$36.46
C$74.74
31
TOPU_KAME_KALIME_KAMEm
Stationary lamp: with emergency power supply, with adjustable lighting, six-reflector
10.0
10 pcs(MEP)
pcs
C$803.32
C$10,161.98
C$8,033.18 +15% C$1,204.98+10% C$923.82
Labor Materials Equipment
Type
Resource
Qty
Unit
Unit Price
Cost
Worker Category 1
309.00
hrs
C$25.98
C$8,026.62
Electricity
22.00
kWh
C$0.30
C$6.56
32
NESA_KAME_KAKANE_MENE
Replacement: two-compartment sinks
1.0
1 set(MEP)
pcs
C$314.54
C$397.90
C$314.54 +15% C$47.18+10% C$36.17
Labor Materials Equipment
Type
Resource
Qty
Unit
Unit Price
Cost
Worker Category 1
3.35
hrs
C$26.14
C$87.56
Cable
0.00
t
C$205,734.40
C$20.55
Dowels
0.00
t
C$183,948.23
C$18.36
Self-tapping steel screws, oxidized, with countersunk head and cross-shaped slot, pointed, diameter 8 mm, length 100 mm
0.00
t
C$117,633.88
C$11.77
Expanding gypsum-clay cement
0.00
t
C$38,461.99
C$3.79
Polyvinyl chloride bushings
0.04
100 pcs
C$4,298.70
C$172.00
Single-mast hoists, load capacity up to 500 kg, lifting height 45 m
0.01
Machine hours
C$2.44
C$0.02
Personnel: 1 person-hour/machine-hour
0.01
Machine hours
C$13.05
C$0.12
Flatbed trucks, load capacity up to 5 tons
0.01
Machine hours
C$26.49
C$0.24
Personnel: 1 person-hour/machine-hour
0.01
Machine hours
C$14.69
C$0.13
33
MERI_KAME_KATOSA_KARI
Installation of a metal drainage system: voronok
1.0
1 set(MEP)
pcs
C$4.84
C$6.12
C$4.84 +15% C$0.73+10% C$0.56
Labor Materials Equipment
Type
Resource
Qty
Unit
Unit Price
Cost
Worker Category 1
0.18
hrs
C$26.88
C$4.84
▼External Works3 itemsC$177,585.47
#
Code
Description
Qty
Unit
Unit Price
Total
34
TOLI_KATO_KATOKA_KATO
Installation of prefabricated reinforced concrete slabs for the unloading platform of Bolverk-type berthing quays in clo
50.0
50 m²(External Works)
m3
C$2,149.84
C$135,977.20
C$107,491.85 +15% C$16,123.78+10% C$12,361.56
Labor Materials Equipment
Type
Resource
Qty
Unit
Unit Price
Cost
Worker Category 1
15.85
hrs
C$18.35
C$290.81
Cranes on crawler tracks, load capacity 50 t
3.85
Machine hours
C$109.51
C$421.07
Personnel: 1 person-hour/machine-hour
3.85
Machine hours
C$14.28
C$54.90
Pneumatic wheeled cranes, lifting capacity 30 t
2.25
Machine hours
C$83.66
C$188.24
Personnel: 1 person-hour/machine-hour
2.25
Machine hours
C$14.28
C$32.13
Flatbed trucks, load capacity up to 15 t
3.38
Machine hours
C$56.17
C$189.57
Personnel: 1 person-hour/machine-hour
3.38
Machine hours
C$11.45
C$38.64
Installation of prefabricated reinforced concrete slabs for the unloading platfo
50.00
m3
C$2,125.53
C$106,276.50
35
KALI_KAME_KASAPU_KANE
Installation of metal fences on reinforced concrete posts: with a mesh panel base over ME.NE to 2 m high
120.0
120 m(External Works)
m
C$270.22
C$41,019.36
C$32,426.37 +15% C$4,863.96+10% C$3,729.03
Labor Materials Equipment
Type
Resource
Qty
Unit
Unit Price
Cost
Worker Category 1
271.20
hrs
C$23.01
C$6,240.83
Ready-mixed masonry mortar, cement, M50
0.01
m3
C$184,460.37
C$2,215.58
Single solid ceramic brick, dimensions 250x120x65 mm, grade M100
0.02
1000 pcs
C$813,259.63
C$19,518.65
Mobile cranes, lifting capacity 16 t
52.45
Machine hours
C$66.34
C$3,479.72
Personnel: 1 person-hour/machine-hour
52.45
Machine hours
C$16.78
C$880.20
Hydraulic diggers
0.58
Machine hours
C$1.51
C$0.87
Flatbed trucks, load capacity up to 5 tons
1.75
Machine hours
C$25.77
C$45.14
Personnel: 1 person-hour/machine-hour
1.75
Machine hours
C$12.49
C$21.88
Welding units with internal combustion engines for manual arc welding, welding current up to 400 A, number of stations 1
5.26
Machine hours
C$4.47
C$23.49
36
KALI_KAME_KASASA_KAPU
Installation of swing gates: with the installation of reinforced concrete posts without foundations
1.0
1 pcs(External Works)
pcs
C$465.54
C$588.91
C$465.54 +15% C$69.83+10% C$53.54
Labor Materials Equipment
Type
Resource
Qty
Unit
Unit Price
Cost
Worker Category 1
9.59
hrs
C$22.22
C$213.07
Welding electrodes for welding low-alloy and carbon steels ANO-6, E42, diameter 6 mm
0.00
t
C$135,142.61
C$40.63
Ready-mixed masonry mortar, cement, M25
0.00
m3
C$4,255.20
C$2.16
Single solid ceramic brick, dimensions 250x120x65 mm, grade M100
0.00
1000 pcs
C$19,596.36
C$21.61
Single-bucket diesel excavators on pneumatic wheels, bucket capacity KA.RISA m3
0.09
Machine hours
C$41.64
C$3.79
Personnel: 1 person-hour/machine-hour
0.09
Machine hours
C$14.02
C$1.28
Mobile cranes, lifting capacity 16 t
2.17
Machine hours
C$66.58
C$144.64
Personnel: 1 person-hour/machine-hour
2.17
Machine hours
C$16.39
C$35.60
Deep vibrators
0.24
Machine hours
C$0.55
C$0.13
Flatbed trucks, load capacity up to 5 tons
0.05
Machine hours
C$25.86
C$1.38
Personnel: 1 person-hour/machine-hour
0.05
Machine hours
C$12.20
C$0.66
Welding machines for manual arc welding, welding current up to 350 A
0.40
Machine hours
C$1.44
C$0.58
Cost Summary
Direct Cost
387%
C$1,942,031.72
Overhead
+15%
C$291,304.76
Profit
+10%
C$223,333.62
Grand Total
C$501,210.21
Resource Summary
134 resourcesiAggregated materials, labor, and equipment needed for the entire project
Materials to Order (82)
Resource
Unit
Qty
Unit Price
Cost
Installation of prefabricated reinforced concrete slabs for the unload
m3
50.00
C$2,125.53
C$106,276.50
Galvanized steel friction wedge anchors for crack-free concrete, exter
10 pcs
124.81
C$409.29
C$51,083.05
Stainless steel collet anchors with conical spacer sleeve for conceale
100 pcs
14.98
C$1,970.64
C$29,520.20
Single solid ceramic brick, dimensions 250x120x65 mm, grade M100
1000 pcs
0.03
C$778,496.41
C$19,540.26
Drill bit with diamond tip for drilling holes for collet anchors, dril
pcs
7.42
C$2,356.82
C$17,487.59
Reinforcement of uphill and drainage ditches, culverts: gutters
m
50.00
C$164.33
C$8,216.46
Low-carbon steel knitting wire
t
0.03
C$213,544.40
C$5,338.61
U-1 slope fastening unit
pcs
48.00
C$49.30
C$2,366.36
Ready-mixed masonry mortar, cement, M50
m3
0.01
C$184,631.67
C$2,215.58
Edged softwood boards, natural moisture content, length RI-NE.SA m, wi
m3
0.02
C$101,445.00
C$1,826.01
Two-component adhesive injection compound based on vinyl ester resin f
l
1.96
C$626.31
C$1,227.56
Spiral drill bits with cylindrical shank made of high-speed steel P6M5
100 pcs
0.39
C$2,647.38
C$1,019.24
Fire-resistant polyurethane foam sealant (assembly foam) for areas wit
pcs
1.52
C$653.40
C$993.17
Galvanized steel rack profile, dimensions 50x50 mm, thickness KA.NE mm
m
162.80
C$6.08
C$990.36
Drying paste-like sealant-adhesive based on organic solvents for seali
kg
10.72
C$83.85
C$898.82
Dry concrete mixes, non-shrinking, fast-setting, containing polymer an
kg
36.00
C$24.64
C$886.94
Bolts with nuts and washers for construction
kg
156.30
C$5.42
C$847.43
Alkali-resistant glass fiber reinforcement tape, width 100 mm, length
pcs
2.12
C$316.27
C$670.50
Galvanized sheet steel, thickness KA.LI mm
t
0.05
C$12,849.20
C$642.46
Self-tapping steel screws with anti-corrosion coating, countersunk hea
1000 pcs
1.62
C$379.53
C$616.73
Welding electrodes for welding low-alloy and carbon steels UONI 13/45,
kg
7.97
C$74.91
C$597.02
Welding electrodes for welding low-alloy and carbon steels ANO-6, E42,
t
0.10
C$5,814.86
C$583.23
Galvanized steel straight hangers for attaching suspended ceilings to
100 pcs
1.75
C$320.37
C$560.64
KN-2 rubber adhesive mastic
kg
66.50
C$8.36
C$555.93
Flat cutting disc, dimensions 125x2.5x22 mm
pcs
37.94
C$9.30
C$352.71
Electricity
kWh
184.59
C$1.89
C$349.45
Universal acrylic sealant for filling joints and cracks, sealing joint
l
0.70
C$432.58
C$303.67
Plywood boards type P1, standard unpolished, formaldehyde emission cla
100 m2
0.51
C$514.04
C$262.16
Galvanized steel guide profile for installing gypsum partitions and su
m
60.40
C$3.85
C$232.48
Steel frame mounting dowels, diameter 10 mm, length 130 (132) mm
10 pcs
1.60
C$132.86
C$212.57
Grand Total
C$259,060.10
Labor Requirements (11)
Resource
Unit
Qty
Unit Price
Cost
Worker Category 1
hrs
2,368.74
C$27.47
C$65,081.01
Grade 4 worker
hrs
1,113.55
C$28.82
C$32,089.75
2nd grade worker
hrs
298.51
C$23.80
C$7,104.08
Personnel: 1 person-hour/machine-hour
Machine hours
265.23
C$16.06
C$4,259.06
Grade 3 worker
hrs
185.81
C$22.65
C$4,209.13
Average workload TO.KA
hrs
109.50
C$20.36
C$2,229.66
Average work load RI.DX
hrs
88.12
C$23.58
C$2,077.87
Personnel: 5 man-hours/machine-hours
Machine hours
26.10
C$61.82
C$1,613.50
Personnel: 3 man-hours/machine-hours
Machine hours
6.30
C$37.09
C$233.68
Grade 6 worker
hrs
2.05
C$36.46
C$74.74
Grade 5 worker
hrs
0.46
C$31.17
C$14.34
Grand Total
C$118,986.82
Equipment Requirements (41)
Resource
Unit
Qty
Unit Price
Cost
Mobile cranes, lifting capacity 16 t
Machine hours
77.65
C$67.45
C$5,237.40
Non-self-propelled floating cranes, 5 t
Machine hours
26.10
C$139.69
C$3,645.82
Crawler cranes, lifting capacity 25 t
Machine hours
27.52
C$96.09
C$2,644.30
Tower cranes, lifting capacity 8 t
Machine hours
26.54
C$38.64
C$1,025.39
Concrete paving machines on rail forms Joint cutters for freshly laid
Machine hours
8.96
C$102.74
C$920.54
Bulldozers, power 59 kW (80 hp)
Machine hours
10.80
C$80.10
C$865.09
Flatbed trucks, load capacity up to 5 tons
Machine hours
31.16
C$23.58
C$734.71
Auto hydraulic lifts, lifting height 12 m
Machine hours
37.20
C$19.64
C$730.75
Tugs, power 221 kW (300 hp)
Machine hours
6.30
C$81.27
C$511.97
Cranes on crawler tracks, load capacity 50 t
Machine hours
3.85
C$109.51
C$421.07
Flatbed trucks, load capacity up to 10 tons
Machine hours
7.33
C$40.34
C$295.89
Trucks, load capacity up to 8 tons
Machine hours
6.00
C$36.17
C$217.05
Pneumatic wheeled cranes, lifting capacity 30 t
Machine hours
2.46
C$83.32
C$204.96
Flatbed trucks, load capacity up to 15 t
Machine hours
3.38
C$56.17
C$189.57
Mobile screw compressors with electric motor, pressure up to KA.NE MPa
Machine hours
23.40
C$4.26
C$99.76
Floating platforms, collapsible, load capacity TO.SA t
Machine hours
4.50
C$19.78
C$89.00
Welding machines for manual arc welding, welding current up to 350 A
Machine hours
43.85
C$1.38
C$60.65
Machines for drilling blind holes for anchors, power ME.PU kW
Machine hours
31.15
C$1.81
C$56.45
General-purpose electric hoists, load capacity KA.SA t
Machine hours
117.08
C$0.33
C$38.39
Welding units with internal combustion engines for manual arc welding,
Machine hours
6.37
C$4.43
C$28.20
Grand Total
C$18,166.66
Material Alternatives
iAlternative materials with approximate price difference. Percentages show material cost change relative to the current specification.
Installation of prefabricated reinforced concrete slabsC$106,276.50
Installation of building frames: box-section frame
2.1%
Envelope
Wall cladding: architectural concrete panels on an
1.8%
External Works
Installation of prefabricated reinforced concrete
1.1%
External Works
Installation of metal fences on reinforced concret
0.1%
Site & Earthworks
Snow removal from construction sites and roads: bu
0.0%
Sensitivity Analysis
±10%iImpact of ±10% change in each cost component on the total project cost
This tornado chart shows how a ±10% change in each cost category affects the total estimate. The wider the bar, the greater the cost impact — helping identify which cost drivers carry the most risk and where tighter cost control may be needed.
Decrease ← → IncreaseImpact
Overhead58% of total
±C$29,130.48±5.8%
Materials52% of total
±C$25,906.01±5.2%
Profit45% of total
±C$22,333.36±4.5%
Labor24% of total
±C$11,898.68±2.4%
Equipment4% of total
±C$1,816.67±0.4%
Cost Summary
iFinal cost breakdown with direct costs, overhead, profit, and grand total
Labor
C$118,986.82
24%
Materials
C$259,060.09
52%
Equipment
C$18,166.69
4%
Direct Cost
C$1,942,031.72
Overhead
C$291,304.76
58%
Profit
C$223,333.62
45%
Grand Total
C$501,210.21
100%
EUR equivalent
€312.670,12
USD equivalent
$360,352.32
GBP equivalent
£272,814.06
Estimate Classification
AACE 18R-97
AACE International Recommended Practice 18R-97
2
ClassClass 2
Typical PurposeCost Control
Expected Accuracy Range:-15% / +20%
Project Definition Level:30–75%
Cost Benchmark
Office · North America
Comparison of estimated cost/m² against market reference ranges
Low 1,800
▲ Typical 2,500
High 3,800
▼ Your Estimate 3,129 EUR/m²
Within typical range · 1.25x ratio to typical
Methodology & Assumptions
iCalculation methodology, data sources, and key assumptions underlying this estimate
Data Source
DDC Pricing DB — English
Confidence Level
50%
Overhead Rate
15%
Profit Rate
10%
Items Matched
36
Assumptions
Costs adjusted by location-specific labor, material, and equipment factors
Exchange rates are offline reference rates and may differ from market rates
All amounts exclude VAT / sales tax
This estimate is for preliminary budgeting only — not a binding quotation
Included in Estimate
All labor, materials, and equipment per defined scope
Overhead and profit margins as specified
Location-adjusted pricing factors applied
Excluded from Estimate
VAT / sales tax
Permits, licenses, and legal fees
Temporary works and site facilities
Design and engineering fees
Prices current as of 2026-03-16 · No cost escalation or inflation adjustment applied
The cost depends on your location, materials chosen, and project scope. Use our calculator with your specific city to get an instant estimate based on 45 verified work items from our database of 55,719 construction prices.
What work items are included in this estimate?
This BOQ includes 45 work items covering Site & Earthworks, Foundations, Steel Structure, Envelope, Openings, Office Area (50 m²). Each item is matched to unit rates from our verified pricing database spanning 9 languages and 36 locations worldwide.
How long does Small Warehouse Construction take?
Duration depends on project size and complexity. A typical 500 m² warehouse + 50 m² office project takes approximately 7 weeks. Our calculator generates a detailed Gantt chart with phase-by-phase scheduling.
How accurate is this estimate?
Our estimates use verified construction pricing data with location-specific adjustments (PPP factors). The Monte Carlo simulation provides P10-P90 confidence intervals. For formal budgeting, we recommend a Class 3 AACE estimate with local contractor quotes.
What does a small warehouse construction include?
Full construction estimate for a 500 m² small warehouse or distribution facility. Covers site preparation, concrete slab-on-grade foundation, steel frame structure, insulated metal panel cladding, loading dock, industrial electrical and lighting, fire sprinkler system, and site works including parking and drainage.