CONSTRUCTION TECHNOLOGY CARD
Монтажные и демонтажные работы

Construction Technology Card: Installation of Precast Reinforced Concrete Hollow-Core Slabs with Construction of an Internal Load-Bearing Frame

This method statement regulates the processes of erecting an internal reinforced concrete frame (columns, girders) and installing hollow-core floor slabs. The document establishes engineering requirements for the production technology, geodetic control, tolerances, and occupational safety, taking into account international quality standards.
6 sections 6 figures

Materials

  • Precast reinforced concrete hollow-core floor slabs (according to the specification)
  • Factory-made reinforced concrete columns and girders
  • Heavy-duty structural concrete, classes C20/25 or C25/30 (grades M300-M400)
  • Stiff cement-sand mortar (for preparing the bedding under slabs)
  • Steel mounting wedges and distribution (flat) bearing pads
  • Welding electrodes for installation welding of steel embedded parts

Equipment

  • Tower crane (lifting capacity according to the weight of the heaviest precast element)
  • Assembly jigs with rotating levers (for temporary fastening of columns)
  • Lifting slings (two-leg for linear elements, four-leg for floor slabs)
  • Geodetic equipment (theodolite, laser level, electronic total station, metal measuring tape)
  • Professional-grade welding machine
  • Modular installation scaffolding and suspended metal ladders
1

Organizational and Technological Parameters and Preparatory Works

The technological process is designed for the erection of structures using a tower crane. The normative framework for a typical work section of 112.5 sq.m establishes the following technical and economic indicators: normative labor intensity is 14.7 man-days (design - 11.7 man-days). Labor intensity per 100 sq.m of clear floor area: normative 10.22 man-days, accepted 8.22 man-days. Output per worker per shift reaches 3.9 sq.m of flooring. The lifting mechanism requirement is estimated at 47.0 machine-hours per 100 sq.m of area.

Prior to the installation of the load-bearing frame, earthworks must be completed, including the excavation of foundation pits, and the bearing base must be prepared in accordance with geotechnical requirements (construction of a compacted sand and concrete cushion). Checking the laying depth and planar position of foundations is carried out using an optical level and a total station, with the mandatory execution of a certificate of hidden works.

Foundation blocks are installed after marking axial lines with indelible paint. The block is lifted by a two-leg sling, stopped at a height of 10-15 cm from the base surface for precise positioning, rotated, and lowered to the design elevation. The joints between the cushions are filled with building sand or cement mortar. A layer of cement mortar approximately 20 mm thick is spread over the installed cushions for the subsequent installation of the reinforced concrete socket (shoe).

Fig. 1 — Cross-section of a refractory-lined industrial furnace wall detailing brick arrangement and expansion joints
Fig. 1 — Cross-section of a refractory-lined industrial furnace wall detailing brick arrangement and expansion joints
1Steel support structure or lintel spanning the upper section to support the roof or upper brickwork
2Expansion joint or compressible refractory filler between brick columns to accommodate thermal expansion
3Main refractory brick lining or blocks forming the primary thermal barrier of the furnace wall
4Base support blocks or skewbacks resting on the foundation structure to distribute the load of the wall
  1. Layout of foundation axes and preparation of the design base.
  2. Marking axial reference lines on the faces of foundation blocks with indelible paint.
  3. Delivery of blocks using a two-leg sling, stopping at a height of 10-15 cm for alignment with the axes.
  4. Laying a 20 mm thick mortar bed and installing the reinforced concrete socket using a four-leg sling.
  5. Backfilling of pits with layer-by-layer soil compaction after geodetic alignment.
2

Installation of Precast Reinforced Concrete Columns

The installation of the lower-tier reinforced concrete columns is performed into the sockets of the foundation blocks. Before installation, alignment marks are made on the column and the socket. The column is fed by a crane, stopped at a height of 0.1-0.2 m above the socket opening, and smoothly lowered. Alignment of the planar position is carried out by matching the marks, and verticality is controlled by two theodolites in perpendicular planes or high-precision plumb bobs.

Temporary fastening and adjustment of the column in the socket are performed by driving reusable steel wedges between the socket walls and the column faces to the calculated depth. After final geodetic alignment, the support node is grouted with structural concrete of class C20/25 or C25/30 (grades M300-M400) according to international quality standards for concrete mixes (e.g., ISO 22966).

The installation of second and subsequent tier columns is carried out on the column heads of previous floors. Special assembly jigs with rotating levers are used for temporary retention and precise adjustment. After securing the column in the jig and aligning it, the steel embedded parts of the shoe and head are welded along the contour in accordance with welding standards (e.g., ISO 17660).

Fig. 1 — Schematic cross-section of a dynamic compaction apparatus and base assembly on prepared soil.
Fig. 2 — Schematic cross-section of a dynamic compaction apparatus and base assembly on prepared soil.
1Steel base plate or foundation block, distributing the impact load over the prepared soil cushion
2Steel anvil or impact block, receiving the direct blows from the drop weight and transferring energy to the base plate
3Outer cylindrical guide casing, secured to the anvil to maintain vertical alignment of the internal components
4Internal guide elements or friction dampeners, centering the central mast within the outer casing
5Central steel mast or ram, guiding the drop weight and ensuring verticality during impact
6Crane lifting mechanism with wire rope and hook block, used for hoisting and releasing the drop weight
7Prepared soil or sand cushion within the excavation, providing a stable working platform and aiding in energy dissipation
8Native subgrade or ground level, containing the excavation and supporting the entire compaction setup
  1. Marking alignment marks on the column and the foundation socket.
  2. Feeding the column by crane (choker hitch slinging or by lifting loops) and suspending it 0.1-0.2 m above the support.
  3. Lowering the column, aligning the axes, and pre-fixing it with reusable wedges.
  4. Geodetic alignment of verticality and grouting the joint with concrete.
  5. For upper tiers: installation of an assembly jig, column fixation, welding of embedded parts.
3

Installation of Large-Size Reinforced Concrete Girders

Installation of reinforced concrete girders begins strictly after the grouting concrete in the column joints has reached at least 70% of its design compressive strength. The girders are placed on the column corbels, forming a rigid internal frame. When installing edge girders, one end rests on the column corbel, and the opposite end is inserted into a specially prepared pocket in the load-bearing brick wall.

Preparation of support nodes in the walls requires high precision. The bearing surface is leveled with cement mortar or fine-grained concrete, and a reinforced concrete or flat distribution bearing pad is installed under the girder end. Elevations of bearing surfaces are checked with a measuring tape from a benchmark and a water level.

Girder installation requires care: the element is stopped at a height of 20-40 cm from the design plane, rotated, and smoothly lowered while controlling the verticality of its faces. Minor adjustments to the planar and axial position are made using pry bars. After installation, welding of steel embedded parts and brick filling of the girder ends in the walls are performed.

Fig. 1 — Lifting arrangement for a prefabricated concrete column with corbels using a rope hitch
Fig. 3 — Lifting arrangement for a prefabricated concrete column with corbels using a rope hitch
1Top column section, rectangular concrete shaft above the corbels
2Corbel or projecting arm, concrete element designed to support structural beams or loads
3Lower column shaft, main vertical concrete support section below the corbels
4Rope hitch, tensioned loop wrapped around the column shaft below the corbels to secure the load for lifting
5Lifting rope or sling, vertical tension member extending from the hitch to the lifting device
  1. Instrumental control of concrete strength in column joints (minimum 70%).
  2. Preparation of bearing pads on corbels and breaking out pockets in load-bearing walls.
  3. Slinging the girder with a two-leg sling and feeding it to the installation site with a suspension at 20-40 cm.
  4. Lowering the girder and adjusting its position with a pry bar according to the applied marks.
  5. Performing installation welding of embedded parts and embedding the support nodes.
4

Installation of Precast Concrete Hollow-Core Floor Slabs

The laying of precast hollow-core slabs is carried out with support on the building's load-bearing walls and the installed reinforced concrete girders of the internal frame. To ensure reliable bearing, pockets 1.5 bricks deep, 1 brick wide, and 5-6 masonry courses high are broken out in the load-bearing walls. A continuous chase 0.5 bricks deep is made in the opposite wall.

Preparation of the bearing zones includes laying a bed of stiff cement mortar along the bottom surface of the pockets and chases with careful alignment of elevations. In heavily loaded nodes, a steel relief beam may be installed. Chases are broken out in sections calculated for the simultaneous installation of 3-4 floor slabs.

Slab installation is carried out using a four-leg sling. Displacement of slab axes and changes in the distance between them relative to the design are permitted by no more than 15 mm. The difference in elevations of the front surfaces of two adjacent slabs in the joint must not exceed 10 mm (for slabs up to 8 m long) and 12 mm (for lengths over 8 m). The bearing depth is strictly regulated by the design documentation.

Fig. 1 — Minimum concrete cover thickness for reinforcement in reinforced concrete columns and foundations
Fig. 4 — Minimum concrete cover thickness for reinforcement in reinforced concrete columns and foundations
1Reinforced concrete column foundation base
2Stepped foundation pedestal for column support
3Reinforced concrete column shaft with corbels
4Top surface of the column shaft
5Bottom edge of the foundation base
7Internal longitudinal reinforcement bars within the column shaft
8Specified protective concrete cover thickness for column reinforcement (values: 20, 25, 30, 40 mm)
9Specified protective concrete cover thickness for foundation reinforcement (values: 14, 16, 20, 24 mm)
  1. Marking and breaking out installation chases (0.5 brick deep) and bearing pockets (1.5 bricks deep) in the walls.
  2. Laying a leveling bed of stiff cement mortar on the bearing surfaces.
  3. Slinging the hollow-core slab with a four-leg sling by the lifting loops.
  4. Laying the slab while controlling the symmetry of the bearing and the gaps between adjacent elements.
  5. Instrumental control of the ceiling surface flatness (tolerance of 2 mm per 1 m of length).
5

Geodetic Quality Control and Acceptance Tolerances

A mandatory condition for conducting installation works is continuous instrumental control of the structure's geometry. The deviation from the alignment of geometric axes marks in the lower section of columns with the layout axes must not exceed 8 mm. The deviation of column axes from the vertical in the upper section is strictly regulated: up to 20 mm for column lengths up to 4 m; up to 25 mm for columns from 4 to 8 m; and up to 40 mm for elements 16-25 m long.

The difference in top elevations of columns (bearing pads of corbels) is limited to a tolerance of 14 mm for columns up to 4 m high, and 16 mm for elements up to 8 m. Deviations in the geometric dimensions of the reinforced concrete floor slabs themselves in thickness must not exceed ±5 mm, and the non-flatness of the lower (ceiling) surface is limited to 8 mm for slabs up to 8 m long.

The use of steel or concrete shims not provided for by the engineering design to level the elevations of elements is strictly prohibited. Reinforced concrete with cracks is not allowed for installation, except for local surface shrinkage cracks with an opening width not exceeding 0.1 mm. The surfaces of embedded parts must be cleaned of concrete laitance and rust.

Fig. 1 — Detail of exterior cladding panel installation with adhesive mortar and support profile
Fig. 5 — Detail of exterior cladding panel installation with adhesive mortar and support profile
1Structural substrate / Wall surface, serving as the primary backing for the cladding system
2Horizontal support profile / L-bracket, securely anchored to the substrate, providing structural support for the base row of panels
3Adhesive mortar layer, applied with a thickness ranging from 5 mm to 10 mm, ensuring structural bond between the panels and the support profile
4Exterior cladding panels (e.g., ceramic, stone, or composite), installed with defined joint gaps (8 mm, 10 mm, or 12 mm) for thermal expansion
5Upper row of cladding panels, aligned and bonded similarly to the lower panels, continuing the facade finish
  1. Checking quality certificates, product passports, and the absence of concrete laitance/chips before lifting.
  2. Geodetic measurement of column verticality after temporary fixation (tolerance 20-40 mm depending on height).
  3. Leveling of elevations of column corbels and wall bearing pads.
  4. Controlling the size of gaps in floor slab joints and the symmetry of their bearing on load-bearing structures.
  5. Recording results in the work log and drawing up an as-built geodetic scheme.
6

Occupational Safety, Health, and Crew Composition

Installation works are performed by a specialized crew of 7 people. The crew includes structural fitters of the 4th grade (1 person), 3rd grade (2 people), 2nd grade (1 person), as well as a rigger and bricklayers. A professional welder certified for working at heights operates outside the main crew. Qualified persons at least 18 years old who have passed safety briefings and hold industrial safety certificates are allowed to work.

Strict weather and spatial restrictions are established. It is prohibited to perform installation works at heights outdoors at wind speeds of 15 m/s or more, as well as during ice storms, thunderstorms, or heavy fog. When moving structures with a crane, the minimum allowable distance to the protruding parts of installed equipment is 1 m horizontally and 0.5 m vertically.

Installed elements must be kept from swaying using taglines made of synthetic or hemp rope. It is strictly forbidden for people to be under a suspended load, on structural elements during their movement, or to leave elements suspended during technological breaks. The movement of workers is permitted only on securely fastened modular scaffolding and floors, the openings in which must be fenced off.

Fig. 1 — Construction site layout plan detailing tower crane operation, material storage zones, and structural component placement
Fig. 6 — Construction site layout plan detailing tower crane operation, material storage zones, and structural component placement
1Cantilevered platform or scaffolding element, providing temporary access or support along the building perimeter
2Storage areas for prefabricated building components or materials, arranged systematically within the site layout
3Main floor or structural slab area under construction, serving as the primary work zone
4Tower crane jib, extending over the construction area for lifting and placing materials and components
5Stacks of prefabricated building elements or construction materials, organized in designated storage zones
6Tower crane base and counterweight structure, positioned on the crane track for stability and mobility
7Crane track or rail system, allowing the tower crane to move longitudinally along the construction site
8Specific storage or staging point for materials, marked as point 'A' in the original diagram, possibly for specialized components
9Specific storage or staging point for materials, marked as point 'B' in the original diagram, likely similar in function to point 8
10Site infrastructure or utility point, marked as point 'B' (Cyrillic V) in the original diagram, possibly a localized service connection
  1. Fencing off the crane's hazardous operating zone with inventory sections and installing warning signs.
  2. Checking the serviceability of safety harnesses, slings, and rigging equipment before the start of the shift.
  3. Using taglines when feeding long elements (columns, girders, slabs).
  4. Exchanging standardized signals between the rigger and the crane operator (the 'Stop' signal can be given by any worker).
  5. Installing inventory covers or guardrails on technological openings in the installed floor.
Tips & Recommendations
i
Engineering recommendation: Do not start the installation of girders and slabs until the instrumental control of the compressive strength of the concrete grouting in the column sockets is completed. The strength must be at least 70% of the concrete class (fck).
!
Critical requirement: The use of random metal plates, wooden wedges, or rebar offcuts to level the elevations of slabs and girders is strictly prohibited. Any compensating shims must be justified by calculation.
!
Safety: Immediately stop lifting operations at wind speeds of 15 m/s or more. It is prohibited to leave precast concrete elements hanging on the crane hook during lunch breaks.
i
Quality control: Before installing floor slabs, clean the bearing surfaces of construction debris, snow, or ice. Applying stiff cement mortar to an ice-covered surface will result in a critical loss of the node's load-bearing capacity.